Tell me more ×
Project Management Stack Exchange is a question and answer site for project managers. It's 100% free, no registration required.

I have a situation where I can have multiple tasks run in parallel but I am short on resources. So let's say I have only two people who can do work on a project. How can I set tasks so dates do not overlap if I use the same resource?

Is there a way project can link these dependent tasks based on the resource assigned to the tasks?

In a nut shell, if I have 10 tasks that take a day each and I have the two people able to do those tasks I want to have a chain of tasks that person A is working strung together with dependencies because some tasks will have to wait for others to be finished, since they all rely on the same resource to complete them all. As a result I should have two chains of five tasks in each person's chain.

Note: I don't want to set these dependencies manually.

share|improve this question
aside from manually setting the dependency my self that is... – kacalapy Jul 19 '11 at 20:24

1 Answer

up vote 2 down vote accepted

I think the specifics depends on the tool on which you working. Generally, however, this is a leveling exercise using a fixed resource or fixed utilization constraint.

In the tool, set your work packages to "fixed utilization" rather than fixed work or fixed duration. Set all work packages to "start as soon as possible." Link all work packages together in the predecessor/successor logic that makes sense, i.e., finish-start, start-start, finish-finish. There is not tool smart enough to be able to automatically establish your hard and soft horizontal and vertical logic of your network diagram. You will have to do much of the sequencing of work manually, allowing the tool to fine tune based on the fixed resource constraint.

Leave no work package as an orphan; all packages need to be linked.

Load your resources and assign the appropriate utilization level, e.g., 100%, 50%, whatever. Assign your resource(s) to the package.

Allow your tool to level the schedule and examine the results. The tool should alert you if it was unable to reconcile a conflict, meaning it scheduled but it may leave a resource over utilized. You will have to manually adjust that.

Since it is fixed utilization, the tool will adjust work and duration to keep all resources at no greater than the assigned utilization factor, except if it was unable to resolve a conflict. The results, however, may be clugy since the tool is only so smart. Likely, you will have to manually adjust.

I would strongly advise, however, not to chase a perfect schedule with no over utilized resources. The second you press start and begin loading actuals, everything changes anyway. So getting close enough is good enough for a PMB.

share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.