I want to enter company holidays in the default working calender in Microsoft Project. But everytime I create new file, I have to re-enter holidays again.

Is there a way to save the holidays, so that when we create new projects, we don't have to define it every time?

share|improve this question
Which version? 2007 or 2010? – SBWorks Oct 5 '11 at 1:56

2 Answers

up vote 1 down vote accepted

With Project 2003 and 2007, the only way I have been able to accomplish this is by changing the working calendar on a project, saving that project as a template, and then sharing the template.

share|improve this answer

Open a current project or new project, change the project calendar and add the calendar to the global file. Saving it as a global file makes the calendar visible to all projects. Steps to add calendar to global file a) Go to Tools => Organizer b) Select Calendar Tab and click Copy.

share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.