We are using JIRA to manage our tasks and to allow our client to review the progress and decides what to do next. Our developers are logging their work pretty accurately.

Ideally our workflow would be the following:

  1. Client asks for a new feature.
  2. We create a JIRA task, assign it to a free developer and do our time estimation and also evaluate how much per hour the client will pay (depends on complexity of the task and experience of the developers).
  3. After some period (a month, or maybe when the new stable version is released) the client gets our report of how many hours each developer has worked and how much the client has to pay.

Problems:

  • there is no "payment for hour" field for the task (this field should be visible only to project admins and the client).
  • there is no plugin or feature, which could use the logged hours
    multiplied by hour rate for each task and generate a report since the date when the client did the last payment.

Because of this, we did some parallel bookkeeping in Excel, but it just seems wrong and takes too much time.

Is there any JIRA plug-in (or any application which uses JIRA database directly) that could help us with such reports?

share|improve this question
1  
Hi Martin, welcome to PMSE! Did you by chance try a Google search or check on Atlassian's website before posting? See the JIRA Timesheet Plugin. I've debated closing this question as "not constructive" since this feels like something that could possibly have been solved with a quick Google search. Since you did include some good details about your problem and since the question really has no other issues other than that, for now, I'll leave it open for our community to decide. – jmort253 Jun 21 '12 at 14:49
One thing that may help is to include details in your question, with another edit, that list what options you did look at and why those options didn't work for you. Welcome to PMSE, and good luck! :) – jmort253 Jun 21 '12 at 14:53
Thanks for welcoming and for the ideas. English is not my native language, so it seems I just used wrong search terms. I looked for reports, work log and that is why I missed timesheet plugins... I guess, "googling" is a skill which needs to be developed :) Then there is just that "pay per hour" issue. I tried custom fields in JIRA, but there is no way to hide them for developers or include in reports... – Martin Sall Jun 21 '12 at 16:57
Absolutely, googling is a very valuable skill in just about any field. If you get stuck trying out any of those plugins you found, I encourage you to edit the question further to update your findings, which makes for a much more targeted and specific question. Thanks for participating! – jmort253 Jun 21 '12 at 17:40

1 Answer

There really isn't a plugin that I know of that does quite what you need. Luckily, JIRA is very extensible. Here's a suggestion.

What I would recommend is to add a custom field in JIRA for Payment for Hour. You do this (in JIRA 5) as follows:

  • Click on the Administration link in the top right corner of the page
  • Issues at the top then Fields
  • Add Custom Field at the top
  • Add a number type field
  • Put it on the screen/project you want, probably a special screen that can only be gotten to by admins

After you have the new field, populate it as desired. Then, when it comes time to run the report, do a JIRA search and whittle down the columns to the description, developer, time spent, and hourly rate. From there, export the output into Excel. It should then be quite trivial for you to add a new column with a formula to multiply the hours against the rate and even sum at the bottom. If adding the field is too much work, you may want to just to just add the rate in Excel directly.

If the field isn't as "admin only" as you'd like, creating an admin only field is pretty much the first and most basic JIRA development tutorial out there:

https://developer.atlassian.com/display/JIRADEV/How+to+create+a+new+Custom+Field+Type

There may be a plugin out there for admin only fields now, but it isn't too hard to do yourself if you have a bit of technical know how and can follow instructions.

share|improve this answer