As subject, on early Monday, I want to see "what we planned to do in this week". At late Friday, I want to see "what has done/delayed in this week".

However, I can't find how to quick-filter tasks like that. How does one do this?

"task in this week" in my context:

  1. Task start in previous week (or before) and finish in this week
  2. Task start in previous week (or before) and finish in next week (or later)
  3. Task start in this week
share|improve this question

2 Answers

up vote 3 down vote accepted

Check your task bar, top right there should be a pull-down menu you can select type of filtering. You will want to filter by "Date Range", you will then be prompted to enter start date and end date of the range.

I don't know how to get to this through the menus.

enter image description here

share|improve this answer

and Here is screen for Microsoft project 2010. for Microsoft project 2010 :

share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.