I have an eye problem, so I want to make the "today line" in my gantt chart to be larger and bolder. Is there any way to do so?

share|improve this question
Not sure about MS Project, but if it were a website you could use a Greasemonkey script to style it however you wanted... – jmort253 Sep 26 '12 at 5:12

2 Answers

up vote 3 down vote accepted

Right click the mouse over a blank space on your gantt graph, choose "gridlines...", highlight "current date" and define the line color and type. I usually make it a red continuous line. Unfortunately, it is not possible to control line width.

share|improve this answer

There is no need of changing it's format. You can just zoom it by simply right clicking the gantt chart space and select "Zoom." That way you can adjust the size of it and view it without any difficulty :)

share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.