Using Microsoft Project 2010, how do I view how much a resource costs the project between a specific time period?
For example, I want to view how much the "HR" resource cost the project between September 13th, 2012 and November 15th, 2012.
|
Using Microsoft Project 2010, how do I view how much a resource costs the project between a specific time period? For example, I want to view how much the "HR" resource cost the project between September 13th, 2012 and November 15th, 2012. |
||||
|
|
|
You should be able to use the costs or custom reports in project 2010 and get reports based on your requirements. |
|||
|
|
|
I have been talking to someone who has used MS project for a while now, as far as he knows this is not possible to do. He suggested I print out the total for each week and add them up manually. |
|||
|
|