Take the 2-minute tour ×
Project Management Stack Exchange is a question and answer site for project managers. It's 100% free, no registration required.

Like most PMs, I wear many hats. The one which fits me better and is consuming more of my time is the Product Manager one, so I would like to start planning for the recruiting and responsibility handover of a dedicated PM so I may better focus on product management.

My vision for this person is for them to be responsible for resource allocation and chasing deliverables, preparing Gantt charts, KPI reporting, etc.

This is a currently small web development team for a large singular website, aiming to be agile.

How big does a team or my workload need to be to justify the onboarding of a dedicated Project Manager so I can focus on Product Management?

I want to avoid being a bottleneck or doing a disservice trying to juggle both roles.

share|improve this question
1  
If you aim to be agile you should maybe embrace a Scrum Master - Product Owner role division –  Picarus Nov 26 '12 at 22:32

1 Answer 1

up vote 2 down vote accepted

Every industry is a bit different. In IT, I think you will find that the cost of PM activities range from 8% to as high 15% of the total CCV. Look at span of control, too. I would suspect you would not have a layer of leadership unless that layer had 6 to maybe 15 direct reports.

If your team is small, looks like a part-time PM.

share|improve this answer
    
I think the number of direct reports makes good sense to me why I would need to continue wearing both hats for the time being. Could you please elaborate on what "CCV" means in this context? –  Leon Stafford Nov 25 '12 at 15:15
1  
CCV is contract cost value, or project budget. –  David Espina Nov 25 '12 at 15:24

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.