I would like to find out the variance between baseline start 1 and actual start. However, I realised that the start variance value as seen from the Variance table actually shows the difference between the baseline and actual start. How should I go about getting this value? Thanks!
Tell me more
×
Project Management Stack Exchange is a question and answer site for
project managers. It's 100% free, no registration required.
|
In "Options", find the EV calculation choice and choose Baseline 1 for your EV calculations. I don't have 2007 anymore so I can't direct you more specifically. But the EV Calculation method is where you need to make the change from baseline to baseline 1. |
|||
|
|
|
Another way to approach this is to save your old schedule as Baseline1, then do your schedule modifications and rebaseline as Baseline. I've found this to be a bit easier to remember to do compared to changing the EVM options. |
|||
|
|