3

I have a project that has 4 team members in the plan:

  • 2 developers @ 8 hours per day
  • 2 developers @ 4 hours per day

How can I configure that two of those dev can only work 4 hours per day but the other two can work 8 hours per day?

Also note: all 4 can do work each day, so I can't simply combine the two 1/2-time devs into a 3rd full-time dev. I need the concurrency of tasks when I auto-schedule

1 Answer 1

4

In MS Project, first list down all your resources and their allocations. This can be done from View > Resource Sheet screen, for example like the screenshot given below:

MS Project Resource Sheet

Then assign tasks to the resources, for example:

MS Project Tasks

MS Project will automatically display that the resource is 50%.

Note that in the sample, Dev4 has been assigned 2 overlapping tasks. This means overallocation which is displayed in red color on the Resource Usage screen.

MS Project Resource Usage

I hope this will be of some help.

2
  • Thanks! In your example on Dev4 being overbooked, is that because you have manually assigned those tasks with those dates? If you were to make Task5 have Task4 as a predecessor and auto-schedule them it would auto-calculate the right dates, right? Thanks again! Jun 14, 2013 at 11:39
  • @MarkUrsino yes, that is right. I manually assigned those tasks with those dates to Dev4 to demonstrate that MS Project shows Dev4 as "Over Allocated". Jun 14, 2013 at 12:42

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.