Cost Management is an organizational methodology by which a company controls and plans the costs of doing business.

learn more… | top users | synonyms

1
vote
1answer
94 views

Formula for calculating cost over a certain time period

How can I calculate the cost of a project over a given amount of time. For example: Solution 1: cost 30k setup and 3k/month for as long as we have the service. Solution 2: cost 40k setup and ...
2
votes
2answers
141 views

Cost of resources in virtual environments

In planning hardware costs, considering the distribution of the product in virtual/cloud environments, where the cost is derived from the use of resources, considering the following points: The ...
2
votes
1answer
66 views

Estimated costs

Should I consider a margin calculating work hours, then increase the final cost, based on estimated hours + margin hours? Or should I add a margin after the estimated hours of work, increasing the ...
1
vote
3answers
368 views

Factors to consider for Merging two or more IT Operations team into ONE

I believe this question falls under a Project from the Management side. But I would appreciate any help or resources for the scenario. The project as an IT Manager, is responsible for ...
1
vote
2answers
171 views

Queuing theory for measuring “change” delivery?

In his presentation "Adopting Continuous Delivery" (http://www.infoq.com/presentations/Adopting-Continuous-Delivery), Jez Humble mentions (~6:50) that queuing theory proves that optimizing for ...
1
vote
2answers
165 views

How to estimate cost to remove bug?

Couple of month before I committed one project to remove bug from that software, that project is not developed according to customer requirements. So, I have included some advanced function according ...
1
vote
2answers
685 views

The meaning of & Calculating Project Budget

I'm very new to the whole Project Management world, so this question may be at the beginners level, anywho: What is the Budget Cost compared to the full Cost of the Project?, based on the research I ...
-1
votes
2answers
156 views

Agile team management strategy for small projects [closed]

I would like to thank StackExchange - Project Management group for providing me with full support and guidance to move forward in my career path. I'm now a Project Manager and a Junior web and ...
1
vote
2answers
457 views

Difference between “Earned Value” and “Contribution Margin”?

I have been searching here and there for the meanings of "Earned Value" and "Contribution Margin", it doesn't seem to make sense to me why so many project could have a positive(+) Contribution Margin, ...
0
votes
2answers
366 views

Microsoft Project: How to represent salaried employees?

I can't figure out how to represent salaried employees in Microsoft Project. I created a 24 month schedule, and assigned a $100/year resource to a 12-month task. I ran into two problems: I expected ...
6
votes
5answers
127 views

Rent total cost prediction

I have a project management course now. One of points of my project requires me to rent a territory, and I need to include its cost in the project's total cost. The first thing I thought was to ...
2
votes
2answers
619 views

Microsoft Project - View Resource Cost for a Specific Timeframe

Using Microsoft Project 2010, how do I view how much a resource costs the project between a specific time period? For example, I want to view how much the "HR" resource cost the project between ...
3
votes
1answer
97 views

Project Planning For Merchant-based Software

I'm quite new to project management. I have a software project in mind and would like to manage it the correct way. The app basically allows movie theater owners to announce their upcoming movies, ...
4
votes
7answers
830 views

Can we use a electronic Kanban board to track actual time spent?

My title sums up my question pretty well. We're investigating whether we can use a Kanban-based system to manage and track some internal projects and one of our requirements is to track time spent on ...
3
votes
2answers
99 views

How can an EV be calculated when there are different versions of a project plan?

There is a project manager who is trying to come up with a way to calculate EV under a specific situation where there is a project management system which allows different versions of project plans. ...
3
votes
7answers
1k views

Should a project Manager include his own cost when costing a project?

Should a project Manager include his own cost when costing a project? I have included the cost of resources I have hired to work on the project, but should I include my own cost to the business in the ...
3
votes
2answers
180 views

Developing a digital strategy

I work in Australia for one of the world's largest companies. Our marketing team has a large budget for IT (information technology) projects but has very little direction or guidance in the way that ...
0
votes
1answer
125 views

What is the cost of a Software Department in a Software Company? [closed]

I'd like to know what is the approximate cost of a software department (Product + R&D) in a typical startup (20 employees)? For example, considering the others departments are sales, accounting, ...
3
votes
2answers
4k views

How to calculate / estimate the cost for one man hour?

I want to know what are all the things need to add for one man hour costing. How to calculate / estimate it?
8
votes
6answers
358 views

What techniques are necessary to convince (upper) management to abandon a project once time has been invested?

I want to convince my manager and (probably) his manager that a project needs to be scrapped and we need to purchase an off-the-shelf solution. Somehow it was recommended that, rather than use a ...
4
votes
4answers
1k views

Is it possible to reduce costs by crashing a project?

I'm working on a study assignment, which involves creating a WBS and GANTT chart for a 6-month project. Then I'm supposed expedite one of the tasks by increasing resources to it, thus decreasing the ...
3
votes
6answers
152 views

What lessons in budgeting a project a PM should remember? [closed]

In budgeting cost of the overall project, what should the PM remember? What are the do's & don't s when dealing with the budget of the project?
7
votes
6answers
816 views

A project manager should know how much his/her project members earn monthly?

A project budget includes fixed and variable costs. In most cases (especially in weak matrix and pure functional organizations) salaries of project members are variable costs. In order to calculate ...
4
votes
2answers
1k views

how to apply the fixed and variable costs on the WBS to estimate the profit?

I have been asked to estimate the profit that could be achieved for a portfolio for IT training courses. I have to estimate the income and the fixed and variable costs and hence the profit. I made ...
6
votes
3answers
742 views

Should every WBS item map to a single “charge number”?

Assuming you are running projects where every employee submits their time in a corporate accounting system like SAP or Deltek, should every project always define charge numbers for every WBS item? ...
4
votes
2answers
108 views

What will be the standard increase of price from a Time and Material to a Fixed Price?

Knowing there are pros and cons for each type of procurement contracts. I am trying to find the real price % increase from a time and material contract with specific scope to a fixed price. As an ...