The tag has no usage guidance.

learn more… | top users | synonyms

3
votes
2answers
69 views

How to handle a part-time kanban team member

A Kanban development team has a WIP limit of 4 on their in-dev column. One of the team members is part-time i.e. not 100% and they are working on a story and therefore holding up 1 spot in the WIP ...
4
votes
1answer
51 views

Resolving impediments caused by other teams

I am a ScrumMaster for a development team. We have an impediment which will be resolved by an engineer on a different team. Does anyone have any tips or techniques for speeding this along. Should I ...
0
votes
1answer
23 views

Automatic Dependency Generator

I have a list of datasets which are required to deliver a large project. The project is comprised of various products. Each product has a requirement for one or more of the datasets. I am want to ...
2
votes
1answer
93 views

Planning backwards in MS Project

I need to plan some activities backwards from a fixed deadline. I am used SF dependencies for that, and there's a slight problem. Let's say I have the following simple plan: 1 Milestone 2 Activity A ...
1
vote
2answers
54 views

Backwards critical path for secondary task path?

I’m using Project 2010, and can’t seem to get Project to do what I want to see. I have a primary task path, call it tasks A, B, C, D. I have another secondary task path, call it tasks 1, 2, 3, 4. ...
1
vote
1answer
240 views

Dependency graph vs. Work-Breakdown-Structure

Let's assume some software consists of 6 components where A, B, C are server side components and D, E, F are client-side components (different user interfaces). The dependency graph is as follows. ...
0
votes
2answers
43 views

I have to plan a launch up against a fixed launch date - how can Project help me understand the LASTEST time I can start on processes

TO keep it simple. I have a hard end date - a milestone. Lets call it 1/1 2016. for the sake of argument lets say I have just one task that needs to be done. That task takes 10 days and must be ...
1
vote
1answer
120 views

ms project shorten summary tasks

I have a number of summary tasks consisting of 4 or 5 subtasks (max 4 days each). These subtasks have dependencies, but the different summary tasks are not dependent on each other. The subtasks are ...
0
votes
2answers
264 views

Create resource dependencies in MS project 2010

e.g. I have a task that has to be fulfilled by two persons, but person B cannot start before person A has finished his part of the task. How do I scedule this in MS project 2010 without having to ...
3
votes
3answers
178 views

How do you deal with client-related hold-ups in Scrum?

Most of our projects get held up by waiting on client assets. Working under waterfall, we're often on many projects at once and can work on something else while waiting. We really want to do scrum ...
1
vote
2answers
155 views

Process for tracking work external to the team?

I'm currently running a project where a very simple Kanban setup (Backlog/Doing/Done) is working great for us—most of the time. But we're also highly dependent on a lot of other teams' ...
1
vote
3answers
2k views

Microsoft Project: Cannot level resources assigned to summary tasks

I have run into unexpected behavior in Microsoft Project 2013. To reproduce, create the tasks seen in the screenshot: Where Requirements has a maximum unit of 100%. Notice that when you "Level ...
10
votes
3answers
1k views

Agile/Scrum- Tracking external dependency stories

Say you have three projects. Two of these projects are end-user facing products (Project A and B). The third is an infrastructure project (Project I) where all the work will never be directly ...
1
vote
1answer
2k views

MS Project 2010 resource dependencies vs task dependencies

How do I make MS Project (2010) distinguish between different kinds of dependencies? For example, consider the following two kinds: Some tasks I mark as dependent on other tasks due to the nature of ...
3
votes
2answers
156 views

How to deal with inhouse technical group manager?

Regarding to management of a multi-task IT project; How to deal with technical group manager who risks the completion of the project in time by not respecting weekly work-schedule?
7
votes
16answers
22k views

“Start to finish” dependency example?

Can you give me an example of a Start to Finish dependency? Wikipedia describes it like this: Start to finish (SF) A SF B = B can't finish before A starts
4
votes
3answers
2k views

Interpretation of 'negative lag' between tasks

I'd like to get your opinion on how you think, intuitively, 'lag' on a depency between two tasks works or should work. To make my point I will start with some examples that are no problem, and ...
4
votes
6answers
6k views

How can a Project Manager manage a dependency on an external team?

A given project team may have a dependency on an external team in order to complete work on their own project. The Boeing 787 Dreamliner project is probably an excellent example of a large project ...