Questions on estimating schedule, costs, etc. go here.

learn more… | top users | synonyms

0
votes
0answers
7 views

What I am accountable for in the management of my project and when?

Do you meet your deadlines staying in budget more than for 95% of your projects?
4
votes
2answers
158 views

Is there any published research about story points vs time estimation?

We're getting started with Scrum and have had a few debates about whether we should estimate in story points or ideal hours. The team is pretty divided, so I'd like to know if any real studies have ...
9
votes
5answers
206 views

How to estimate time required and deadlines for creative and problem-solving tasks?

How to quantify time requirements for tasks that are almost purely problem-solving or creative? And how to set deadlines based on those estimates? Practical scenario in my team: Steve must find a ...
1
vote
2answers
119 views

How can I determine a project end date when PBIs are not estimated?

How can I determine a project end date when Product Backlog Items (PBIs) are not estimated? Consider the following two examples: I am on a project that is at the beginning. I'm asked when the ...
3
votes
1answer
159 views

Small firm with 4 developers and 2 project managers in need of some guidance for project workflow

I work as a developer in a small IT firm with 4 developers and 2 project managers. We currently implement some sort of traditional project management, in which the workflow for a given project is as ...
7
votes
4answers
219 views

When can a project's wrong estimates be justified?

This question is not about project estimation techniques, initial processes, etc. Assume everything was done correctly. Recently, we gave an estimation for an Android application with development ...
1
vote
1answer
70 views

Estimating the resource usage breakdown of a project at initial proposal time?

How can one estimate the resource usage breakdown of a project at initial proposal time? For example in fixed price project, say a ten-member team project with project duration 12 months 1 PM 1 ...
2
votes
1answer
69 views

Re-Estimating a story's points midway through a timebox

I have recently come across this situation: user stories are estimated using story points timebox planning session has taken place and everything is agreed on timebox (three weeks) is in week three ...
5
votes
5answers
229 views

Estimating user stories at the start of the project so that the PM can determine a quote for the client

Recently I have started on a team in a new project. Our company is attempting to run things in an Agile manner. The project consists of 4 developers each from different teams and with different ...
3
votes
6answers
265 views

Why not use costs instead of story points for estimation?

I propose the following scheme for estimating user stories in a scrum process: A good programmer might cost 80000$ a year, so per hour this is 80000$/52 weeks/40 hours per week = 40$ per hour. In a ...
5
votes
5answers
330 views

Constantly under-estimating user stories

I'm the dev manager in my company. We're following what some people in the company like to call "scrum" but is in fact waterfall in scrum clothing - we are using some scrum terminology (backlog, ...
1
vote
4answers
142 views

Should I remove distraction time from developers' capacity time while giving time estimation?

I am about to give new estimations of a project delivery time, estimating iterations etc.. Besides development, developers spend much time on distractions. By distractions I mean everything(tea, ...
7
votes
2answers
139 views

Agile estimation and communication of price to customers

I'm new to this Agile way of doing estimates. For a long time I have been working in the classical way of estimating the whole project up front (roughly). Now I have started to look into the Agile ...
7
votes
4answers
749 views

when a software project is behind schedule should we add manpower?

When an essential software project is behind schedule we might naturally add manpower. The new developer, however competent and however quickly recruited, needs additional training from an ...
0
votes
3answers
199 views

How can I plan a project that has undefined scope associated with learning new skills?

The client has set (and we have agreed to) the deadline for a project. In order to complete the project, the team needs to master a new tool chain including Selenium and Java. How do I establish a ...
2
votes
2answers
134 views

Cost of resources in virtual environments

In planning hardware costs, considering the distribution of the product in virtual/cloud environments, where the cost is derived from the use of resources, considering the following points: The ...
0
votes
2answers
140 views

What ways have you reduced cost for a software project during the planning phase?

I am getting ready to head up an internal project. I already know that the budget will be tight on this. I am looking for effective ways to reduce project cost. What I would like to see is the most ...
2
votes
5answers
228 views

Calculating time needed for finishing project from scratch [closed]

I want to calculate or estimate time needed to code a particular project. This may include time spent doing analysis, actually coding etc. I find it difficult to make a good estimate. Can someone help ...
0
votes
3answers
315 views

How to prevent top managers setting unrealistic expectations with a customer?

Currently we're working on a project where top management is providing unrealistic estimates to our customers, especially in terms of the number of bugs that we can fix. We are not talking just about ...
2
votes
2answers
259 views

How can we estimate the learning curve for new technology in a project?

I work with embedded systems and sometimes there are some technologies that the people involved with the project have to learn before applying to the product. We are three people that never worked ...
1
vote
1answer
142 views

What pro forma documents do people use to talk to clients about web development

This is a very general question and I believe it will be relevant to other people in my situation. I've been involved as a hobbyist in web design and development for over 2 years now. I have produced ...
3
votes
2answers
313 views

Getting estimated working time from MS Project

Our company has just recently started using MS Project Professional 2010 and we plan to eventually have a Project Server installation. I've created a few projects so far, but still claim to be a ...
0
votes
1answer
124 views

Functional vs Non-functional requirements: Standard proportion of time spending

I have an application that have no unit tests. There are performed only manual tests through UI clicking. There is also a lot of spaghetti code, runtime evalutions, duck castings, old versions of ...
4
votes
2answers
409 views

Is it a good Scrum practice to use large story-point numbers for effort estimation?

Is it generally a good practice to have large story-points for user stories in a sprint? We are following a modified Fibonacci series of 1, 2, 3, 5, 8, 13, 20, 40, 100. We estimate the effort ...
1
vote
2answers
252 views

For every hour cutting code, how many project hours are spent doing something else?

I work on a large line-of-business legacy application, my projects are very much NOT green field. The dev teams are small, usually 2 developers, 1 system tester, plus part-time PM and BA resources. ...
2
votes
3answers
353 views

Should there be testing-only user stories?

We estimate stories as 1, 2, 4, 6, or 8 points. Consider a story with less development work but huge testing effort. Let's say we estimate that story as 8 points. We see the following options: ...
0
votes
2answers
149 views

How can we manage schedule risks brought into a project by 3rd party software?

Working in web-development, I face a common situation when clients want to use 3rd party software as a starting point of the project. That could be a CMS, an e-commerce site, or something else. ...
0
votes
4answers
832 views

How can I get inexperienced team members to meet project deadlines?

Recently, we have hired bunch of people who say they have little experience on technology. When I delegate jobs to them and ask for a timeline, they give unrealistic timelines of around 3-5 months. I ...
1
vote
2answers
160 views

How to estimate cost to remove bug?

Couple of month before I committed one project to remove bug from that software, that project is not developed according to customer requirements. So, I have included some advanced function according ...
3
votes
3answers
577 views

What are Our Alternatives to Function Point Analysis for Estimation?

We've been using Function Point Analysis (FPA) estimation for new software development projects and medium sized changes that involves development efforts for code involving database entities as well ...
3
votes
1answer
750 views

Does the team estimate time for tasks or stories or both?

During the sprint planning meeting, does the team estimate time for each story, or the tasks that make up the story? Then which is tracked by the team/scrum master? I assume the team estimates the ...
2
votes
5answers
174 views

Can story points remain constant between the initial estimate and later planning sessions?

Background We have a bunch of epic stories. We have a fixed term to do the project. We have to get approval from a project board. We don't know the velocity of the project team yet. The ...
1
vote
2answers
461 views

When should I assign 0 and 0.5 story points to user stories in Scrum?

I am not a Scrum Master or a Ph.D. in math. How do stories with 0 and 0.5 points apply to stories on the Scrum board?
1
vote
2answers
644 views

The meaning of & Calculating Project Budget

I'm very new to the whole Project Management world, so this question may be at the beginners level, anywho: What is the Budget Cost compared to the full Cost of the Project?, based on the research I ...
1
vote
2answers
919 views

Who should estimate user stories?

Should the product owner take part in estimating user stories? Furthermore, in our team not all developer familiar with every part of the system. Client and server side is a usual separation. GUI ...
5
votes
5answers
637 views

How to sequence tasks given time estimates?

What are the recommended techniques to get the fastest completion time? Just an example, a project has 6 tasks: task1 takes 1 day task2 takes 2 days task3 takes 3 days, requires both task1 and ...
2
votes
1answer
310 views

Should the Kanban CFD be weighted with estimates?

I am working in a Kanban process with a team the tries to estimate Cycle time, Lead time as well as completion time based on applying FIFO wherever possible on our queues. Using the Cumulative Flow ...
-1
votes
1answer
138 views

How to Estimate Scope, Cost and Budget for Developing a Phone App

I have some questions regarding how to handle bidding for a project, and how to structure the contract for the project. How can I find the answers to the following questions: How many people ...
2
votes
2answers
166 views

Quickly explain how to make estimation work to an external business stakeholder

Scenario: need to quickly explain how the estimation will work to an external business stakeholder; can't take more than few minutes really. The project area is web development. P.S. There's no point ...
1
vote
4answers
675 views

How can we transition to Agile estimation based on complexity or effort of user stories?

We have being practicing agile development methodologies for a long time as a development company. Most of the time our product owners tries to have a map between story points and time. As a example, ...
4
votes
4answers
269 views

Schedule Control

Here's the scenario: You are building a schedule for a project that has a planned duration about three months. You are not concerned about project costs so you will not be doing EV. You are ...
1
vote
5answers
602 views

First sprint: Epics chosen instead of stories - should I re-estimate and when?

I am trying out Scrum on a small, one-person project. During my first sprint, I realized that all of the stories I've chosen are really epics and should be broken down into much smaller pieces. The ...
2
votes
4answers
2k views

How to estimate accurate velocity when team members are on leave

I am a Scrum Master of a team with 12 members. I know that the size of the team is large at this point, but as we grow further we will divide the team into multiple Scrum Teams. Our estimations for ...
1
vote
4answers
195 views

How to compare and select one project out of two?

It's being rather a tough choice on selecting projects. (Different case from what I had posted before.) Now in the scenario if there is Project A and B. Only one project can be executed and that has ...
4
votes
3answers
271 views

How does a team (new to product and domain) estimate user stories of a ten year old product?

I am the scrum master for one of the products in a software development company. Our team, including me, operates from India. However my product owner is in USA. We are working on the feature ...
4
votes
4answers
845 views

How can developers and testers agree on story point estimates?

Previously we used duration for each story, but in our current sprint we are using story points (effort) keeping test team effort separate from the development team effort. Story points are based on ...
8
votes
3answers
1k views

In Scrum, how to estimate research stories?

In our Scrum team, when there is uncertainty about a story or the team is not sure about how to implement it, we take up a research story first. Based on the findings of this research story, we are ...
2
votes
3answers
625 views

Alternative schedules in Microsoft Project 2010?

I'd like to create a "reference" schedule, then create an optimistic and pessimistic schedule based on this where the duration of each task in the optimistic/pessimistic schedules are calculated as a ...
1
vote
4answers
2k views

Modelling schedule uncertainty in Microsoft Project 2010+

Microsoft Project 2010 (and 2013) no longer contain PERT charts. With this in mind, what is the recommended way to model uncertainty in project time estimates? UPDATE: I only brought up PERT diagrams ...
8
votes
6answers
467 views

Why use iterations in Scrum?

I am a Scrum Master in a 7 person team. We currently use one-week iterations for our sprints. I find that sprint planning overhead is huge (2 hours each week for entire team), and not nearly as ...