Earned Value Management

learn more… | top users | synonyms

2
votes
3answers
303 views

What is the best way to develop a project baseline?

I am conflicted on how to create a baseline for a project. Which of the following scenarios would be considered a "best practice" for creating a project baseline in which to measure progress and get ...
1
vote
3answers
267 views

Can EVM be Used to Track and Manage Quality?

Currently, I think I've got pretty good tools when it comes to measuring Budget (enough and more Excel docs that are regularly updated), Scope (against a mutually agreed upon statement of work), Time ...
3
votes
4answers
239 views

What is a good way to set control limits on a schedule?

I want to try to track project progress using Earned Value Management approaches, mainly for my own education rather than out of a pressing need. The metric used to define planned value (PV) and ...
1
vote
1answer
267 views

Can MS Project graph out planned value?

I would like to create a graph like the one below dynamically in Project. I have done this in the past using Excel, but in those cases it was "easy" since planned and earned value were calculated ...
2
votes
1answer
263 views

Creating an Agile Estimate for an Earned Value Management PMB

Earned Value Management is predicated on the creation of a Performance Management Baseline (PMB). The PMB can be thought of as a super estimate that defines what work is planned to be done by what ...
1
vote
2answers
195 views

How do you handle new tasks in an earned value analysis chart?

Earned Value Analysis is great on paper. However, I'm having difficulty using it for programming projects that tend to change dramatically from week to week. For example, a milestone is "complete ...
2
votes
2answers
381 views

Good resources on applying Earned Value Management

Two part question - First - I have a basic understanding of Earned Value Management (EVM), but the example I've found so far on applying seem vague. So any suggestions on understanding EVM more? I'm ...