This tag is for all questions that involve Microsoft Project. Specify the version you are using in case the answer is different for different versions.

learn more… | top users | synonyms

0
votes
1answer
13 views

MSP 2010 - duplicating tasks and logic

I have a schedule I am putting together for a repeating layout multi-floor building. Is there any easy way to copy the tasks and their predecessors and successors from say floor 2 and with minor ...
0
votes
1answer
20 views

MS Project: how to distribute remaining work equally

I have an effort driven task which should take 20 days, to which I assigned 2 resources. Initially, the work got distributed equally between them (10d each). During the first week of work there were ...
0
votes
0answers
12 views

MS Project - Marking task as complete causes resource over-allocation

I am struggling to understand what is causing a specific behavior in MS Project. I have a project that is planned out and the work has begun. When I complete a task, I mark it as 100% complete. The ...
0
votes
1answer
39 views

Microsoft Project views

I'm pretty new to Microsoft Project and I'm trying to put several views in place. However, for some reason, if I edit one view (Issue Log view) my Gantt Chart view gets the same updates. So if I ...
2
votes
2answers
75 views

Interviewing for MS Project skills

I'm assisting with interviewing a few new PM candidates, and I've been given the task of asking questions related to their MS Project knowledge. The other interviewers are using experience-based ...
0
votes
1answer
50 views

In Microsoft Project why is my actual duration calculating to 0 days?

I had set a baseline previously and I am now updating to show what has actually happened. I went into the task information and changed the "start" and "finish" dates to what actually happened. When ...
2
votes
1answer
49 views

MS Project - Span a task over many days AND allow successor to start right after

I am planning my Master thesis through Microsoft Project. Since some tasks can be exhausting (e.g. writing), I would like to distribute some selected tasks over many days. For example, I am estimating ...
0
votes
0answers
11 views

Can't set background color of manually scheduled tasks in network view

I'm using Project Professional 2016 on Windows 10 to model university courses in a bachelor's degree. Courses are tasks, and pre-requisites are predecessors. This is all wonderfully shown in the ...
1
vote
1answer
33 views

How to force ms-project to reschedule when all resources are available?

I'm currently trying to setup a meeting in ms-project with 2 resources: Alice and Bob Alice's calendar is based on the standard calendar (working every weekday): And Bob's calendar is based on the ...
0
votes
1answer
29 views

Working (part of) an MS Project schedule backwards

I'm trying to make a portion of my MS Project schedule work backwards, and it's not working quite right. I'm hoping you can help. I have a schedule where Task 45 ends on 2/1/17. Tasks 46 through 50 ...
0
votes
1answer
39 views

Fixed work which means work hours remains unchanged irrespective of increase in duration when updated

Using MS Project 2013, I would like to express the following situation. I have schedule/tasks set to fixed work which means work hours remains unchanged irrespective of the increase in duration when ...
0
votes
1answer
81 views

Calculating the Difference Between Actual Start Date and Baseline Start Date

I'm new to MS Project. I want to calculate the difference between the baseline start date and the actual start date. Does anyone know how to calculate that? I've seen in another forum that I need to ...
0
votes
1answer
52 views

Part time project member: how to specify his 20 hours a week?

Hello Stack Exchange colleagues. I'm trying to set up a project that has 3 full time project staff and 2 part time staff (students). The way I'm planning is that all tasks are common to any of ...
0
votes
1answer
71 views

Ms project, how to calculate difference between actual duration and duration?

Ms project, how to calculate difference between actual duration and duration ? i mean for example: if any resource finish the task before the actual finish date , how can i calculate this overtime ???...
0
votes
0answers
36 views

What possible gotchas what I can expect from using MS project for timesheet/billing?

My concern is use of MS Project for employee time sheet, billing, planning and tracking work time on people/resources (developers, IT engineers) over a time under multiple "service contracts" instead ...
0
votes
1answer
77 views

Start-to-Start and Finish-to-Finish Logic in MS Project

Let's say I have three tasks. I want Task2 (hammock activity) to start at the same time as Task1 but finish at the same time as Task3. Is there a clever way of doing this? This task will adjust it's ...
0
votes
1answer
96 views

Why is MS Project 2016 Showing a $0 for BCWP on a completed task

I am not understanding how MS Project (2016, in this case) calculates the BCWP component of Earned Value. To illustrate: below is a one-task project. The task is five days long, has one resource ...
0
votes
1answer
29 views

Custom Field Formula for MSP

If( [Text1] And [Text4] > 0, [Text1] - [Text4], "" ) I need a syntax for Null/Empty cells in [Text1] and [Text4] to avoid #ERROR Thank You
1
vote
3answers
63 views

How to estimate number of resources when I have my timelines fixed, but work effort is more

My total work estimate is 1056 man days Release Start time: May 10 Release End time: October 10 total Work days available: 101 1056 / 101 = 11 resource Approx. Is this correct calculation? If not ...
0
votes
2answers
28 views

Drop-down menus in MS Project 2013 disappeared

In one of my MS Project 2013 files, the drop down menus appear when I hover over the column headers in the Task Sheet view. In another file and new files, the drop down menu option does not appear in ...
0
votes
1answer
18 views

Is there a way to links tasks that have overlapped dates?

for example, if I have two tasks start at different dates that end at the same date. My problem is, if I try to link these two tasks, the dates will automatically change, not the original dates I ...
1
vote
1answer
54 views

Why can't the Crash Time be greater or equal to Normal Time?

Scenario Activity | Normal Cost | Normal Time | Crash Cost | Crash Time | Weekly Crash Cost A 5,000 4 5,000 4 0 B 8,000 4 ...
1
vote
1answer
50 views

PWA / Enterprise custom columns - formula not working

I'm using Project Online and am trying to create a custom calculated column which shows me the percentage difference between my "Actual Cost" and a custom column called "Profitability". I'm having ...
0
votes
2answers
42 views

MS Project 2016 is returning too many hours in summary tasks for Work

I am using MS Project 2016. Summary calculations for duration are all correct, but SOME of the summary calculations for Work are double or quadruple what they should be, as if it's including subtotals ...
1
vote
2answers
101 views

How can our chaotic JIRA process be used to report resource allocation using MS Project Server?

I'm trying to figure out the best method to address this issue. We have a pool of resources that work on projects, BAU, and production support. PMs utilize these resources in an agile methodology and ...
1
vote
1answer
54 views

Resource Allocation - Two resources on one task at different ratios

I have a project where I am setting resources at 60% availability in general. However, for certain tasks, I would like to divide the work proportionally between two resources. The best way I can ...
0
votes
1answer
64 views

Using MS project for overview with TFS to control the details of a mechanical development project

My group is using TFS for resource commitments. To get a clear overview of the project schedule I would like to use a Gantt chart in MS Project with 3 week sprint periods so we can see how we are ...
0
votes
3answers
215 views

in MSP 2010 How to change task duration units from weeks to days in bulk

I'm dealing with a large plan developed by different people and it has some durations in days and some in weeks, but I'd like to unify them all in days. what is the best way to do this in MS Project ...
1
vote
4answers
108 views

How can I do Change Request on Microsoft Project?

Title is self-explanatory. MS Project 2013 for reference. I'm not allowed to disclose many details of the project, but it's a small/medium scale IT project with a team of 6 people. I have everything ...
0
votes
1answer
114 views

PWA's Project Center Timeline Not Adding Tasks or Projects After Editing Webpart

My organization uses Project Web App integrated with Sharepoint task lists to share project plans and delivery schedules. Project Web App's Project Center has an aggregate timeline feature, which ...
0
votes
0answers
39 views

Link a task to begin when the first of some tasks begins [duplicate]

In MSProject, I'm trying to link one task (let's say Task A) so it begins when the first of multiple tasks begins (let's say Task B & C). Start-Start links make my Task A begin when both Tasks B ...
0
votes
2answers
62 views

How to cope with milestones that can only occur every two weeks?

In MS Project... I have a project that will ultimately be released by a third party, who have their own, fixed release schedule. The releases happen every two weeks. How can I attach the end of the ...
0
votes
3answers
239 views

How to stop ms-project from changing task dates

I am running into a strange problem with project and was wondering if anyone has been able to solve this problem. I don't want project to change any of my dates based on changing %complete OR have ...
1
vote
2answers
119 views

How to force one task to end at the same time as another task in MS Project

How do I force one task to end at the same time as another task. We have "User Acceptance Testing" ending on a specific date so I want the "Bug Fixing" task to end on that same date. I.e. the ...
2
votes
3answers
136 views

Is there a way to copy and paste tasks from one project file to the other without losing the predecessors?

I am currently running a project to develop about 50 parts. Each part has about 100 actions from engineering to production to shipping. I created one standard project file for a standard part. Then I ...
0
votes
2answers
104 views

Microsoft Project - view resources in hours not percentage

I had assigned resources to tasks in Microsoft Project gantt chart and I would like to see them in hours per resource, not percentages. I know that I can see hours in Resource Usage chart, but maybe ...
1
vote
4answers
140 views

In MS Project, how do I create a task to start with the earliest of two dependencies?

I have two tasks in Project: let's say task A's start is 1/30 and task B's start is 1/25 (end dates don't matter here). I need to create task C, which starts at the earliest possible time - in this ...
0
votes
1answer
129 views

MS Project 2013 resource graph

I am using the standard calendar. Have a resource available 100% of the time. When I add the first task, a 1 hr task, when I look at the resource graph it shows at 100%, I have it set for an 8 hour ...
0
votes
1answer
55 views

Need task to ignore schedule

I have a situation where we will be doing a conversion over a weekend in order to minimize impact to the company. Additionally, this task should be delayed until 3 weeks after a predecessor task. What ...
0
votes
2answers
78 views

How to represent tasks with subtasks over versions?

I have tasks T1, T2,...TN. Each task has subtasks S11,S12,...,SNM. Each subtask takes some amount of time. For version V1 I have t1 months, for version V2 I have t2 months,... For simplicity I assume ...
0
votes
1answer
44 views

Microsoft Project - Problem synchronizing summary tasks around a milestone

In my project, I have dozens of summary tasks which are comprised of sub-tasks of different durations. e.g. SummaryTask_1 Phase 1 SubTask1a --> d1 SubTask1b --> d2 Phase 2 SubTask2a --> d3 ...
0
votes
1answer
82 views

Inherited Project Fix or Start Over

I inherited a 1265 line project that I believe was created in Project 2007 several years ago (~2013). It is now in Project 2010 and has had several different people working on it, along with periods ...
4
votes
3answers
332 views

What is the purpose of the “as late as possible” constraint in MS Project?

I understand that I can use this constraint in MS Project, but really, what is a good use case for this? When does this constraint make sense?
0
votes
2answers
105 views

Adding unnumbered task in MS Project 2013

I need to add a task to my WBS/Gantt Chart in MS Project, but not number it as it is a task (Kickoff meeting) that I want to fall under the heading: Project Administration. I need this to be a general ...
1
vote
1answer
89 views

Creating a Template in MS Project

My work consists of a number of nearly identical projects and I'm wondering if I can create some kind of template in Microsoft Project. Hopefully this isn't too stupid a question as I've only ever ...
0
votes
0answers
49 views

Microsoft Project 2013 - Resource Plans - Allocation Discrepancies using Multiple Units

Within the Microsoft Project Server 2013 Resource Plan, I am experiencing unexpected results for planned hours when toggling the Units used for different resources. Scenario: Two resources on a ...
0
votes
1answer
59 views

'Early Start' equals actual start date

I am working on a project and the 'Early Start' column reads exactly the same as the actual 'start' column (following team assignment and task scheduling) for some fields. I understand that the early ...
0
votes
1answer
194 views

Print a MS Project Gantt chart for each resource

I wonder if there is a function in MS Project to print the Gantt chart view for each resource, i.e., when issuing the schedule to everyone I print to PDF: Complete Schedule Summaries only Each ...
1
vote
2answers
464 views

How to assign multiple resources to a in MS Project and making them work different hours over the same duration

I am trying to load resources into tasks in MS Project 2013 Standard. The tasks have specific durations for when they should start and end. For each task, I would like to assign multiple resources and ...
1
vote
1answer
51 views

In resource allocation, how do you call the group of people that will be hired in the future?

In other words, in my "MS Project-like tool", I have teams with the people that I've already hired, and unassigned people mark as in the "bench" team. I'm looking for a placeholder team name to put ...