Tagged Questions

This tag is for all questions that involve Microsoft Project. Specify the version you are using in case the answer is different for different versions.

learn more… | top users | synonyms

0
votes
0answers
9 views

Remaining work roll up value incorrect after refreshing TFS data in MS Project

I have problem importing TFS data into MS Project that is driving me crazy. When I first import TFS data into a new project all the roll up values for remaining work in MS Project are correct, but ...
0
votes
2answers
84 views

Finding the minimum number of functional teams needed to do repetitive tasks

I have a Project Plan in MS Project, its a construction project which has repetitive tasks and multiple gangs. For example: Building 1 Strip Clean Paint Varnish Building 2 Strip Clean Paint ...
-2
votes
0answers
22 views

Adding Additional Cost to MS Project

I have a question where the Finance Department has asked to add the following additional cost to the MS project. Administrative Cost of 2600 dollars per week (to be paid at start of the week i.e. ...
0
votes
1answer
34 views

Duration of Recurring Tasks in MS Project

I have set up a recurring task to recur every 4 weeks for 4 occurrences. To me, this means the duration should be 4 x 4 x 7 = 112 days, but the duration is set to 253 days. Can someone explain?
0
votes
0answers
33 views

Master Project with Subprojects - need to share master but without the subprojects included

I have a master project which contains 11 sub projects. Whenever I send the master project to anyone, I have to send all the 11 sub project MPPs out to them too. Is there a way of creating the master ...
2
votes
1answer
73 views

MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table

Software Version: Microsoft Project 2013 Standard (15.0.4420.1017) Hello - I am creating a report in MS Project 2013. When I create a time-phased line chart containing ACWP, the ACWP shown in the ...
0
votes
1answer
45 views

Gaps in resource scheduled time

I'm attempting to use the "Level All" button in MS Project 2013 Professional. There are three resources, which you can see in the screenshot, with two of the resources working on the same item, shown ...
0
votes
1answer
37 views

Tasks on my Project do not print

I am using MS Project at work, and I noticed on one job when i print the calendar, certain tasks do not show up. It appears that every task that is lower in the day cell does not show up on the Print. ...
0
votes
0answers
56 views

Resource usage total doesn't match Gantt chart total

I have an MS Project file where the total value of the effort calculated by adding up each resource in the Resource Usage sheet is greater than the total effort of the tasks in the Gantt chart. I've ...
1
vote
2answers
58 views

Scheduling not calculating properly [closed]

In Office version 2007, I have some tasks that are all fixed duration. I'm a prime contractor with subcontractors and I'm trying to schedule out events. I have add the duration and assigned the ...
1
vote
1answer
45 views

Using MS Project 2007 for Manufacturing Build Time

Is there a way for MS Project 2007 to calculate durations based on a give time/part and total number of parts. For example: A manufacturing process can process 1 part every 30 sec and we want to ...
0
votes
2answers
44 views

MS-Project 2010 - How to add Task Name to the Quick Access ribbon?

I used to love the fact that there was a text editing box at the top of the screen in old versions of MS-P, allowing you to edit Task Name directly without having to open the Task Information dialog. ...
0
votes
1answer
43 views

How to configure resources that work different max hours per day

I have three groups of resources: Group one - onshore permanent employees that work 7.5 hours max per day Group two - onshore contact employees that work 8 hours max per day Group three - offshore ...
0
votes
1answer
90 views

Microsoft Project, total resource usage by group

I have Project 365 and I am trying to create a view where a task will display all the resources it uses, and then total them by group. For example I have the Group "labour" where I've put all my ...
0
votes
2answers
94 views

Planned work until date in MS Project 2007

I want to know the Planned work until the status date to compare with the Earned work done to this date. It is a value calculated in ARTEMIS , but I'm new in MS Project and I don't find it. Like the ...
0
votes
1answer
85 views

MS-Project: any ideas on how to approach defining a MINIMUM work assignment per day for resources?

I am currently working on a high level project plan with all our department's projects and resources allocated to each project (roughly like 10% during 2 months, 20% during 2 weeks, etc.). This is to ...
0
votes
1answer
82 views

Calculating a running sum of subtask cost amounts

How can a Summary task reflect a running sum of subtask input amounts?
0
votes
1answer
125 views

MS-Project 2010: Task end-date seems to be calcuated incorrectly

I am using MS-Project 2010 and have noticed something peculiar in how "end-date" of the task is dislayed. I obeserve the following behavior: 1. I set the task to start on Monday. 2. I set the ...
1
vote
1answer
73 views

How can I convert existing tasks and subtasks to subprojects in Project 2010

I understand how to create a subproject and insert the subproject into a master project. Is there a way to take an existing task (and its subtasks) in a master project and convert them to a new ...
0
votes
1answer
48 views

Working with a Shared Resource Pool and project plan revisions

We have a practice of saving a copy of our project plan with the status date in the filename every time we update status. This messes up the shared resource pool, because the resource pool now thinks ...
0
votes
1answer
261 views

Change default Task Type to 'Fixed Work' in Microsoft Project 2013

When I create a new task in Microsoft Project it defaults to "Fixed Units", however most of the projects we do are estimated upfront so we need to schedule based on fixed amount of effort but variable ...
2
votes
2answers
118 views

MS Project Elapsed Day Task Ends on Weekend

I am currently working on a project where a task requires a block of time to achieve a total amount of exposure, so I've been using the elapsed days duration function. In this case, the task requires ...
2
votes
3answers
157 views

Handling resources who do not have 100% availability in MS Project 2003

This is a technical question regarding Microsoft Project 2003. I am trying to schedule resources who have other (management) duties not related to the project. My initial thought was to reduce their ...
0
votes
2answers
136 views

Let MS Project adjust previous dependent tasks' schedule based on last task's due date

I want to tet MS Project adjust previous dependent tasks' schedule based on last task's due date. I'll try to tell my requirement via image below: last row is a milestone (final report) and has a due ...
0
votes
3answers
106 views

Allow resources to pick assignments on a day to day basis?

In our organisation, we're using a MS Project Server setup that's pretty much out of the box. I'm now struggling to find a fit with one of the requirements put forward by our PMO: Our company has ...
3
votes
2answers
134 views

How to save Gantt and PERT as a GIF image?

I'm working with MS Project, and I have created a Gantt chart. How would I save a Gantt and PERT file as a GIF image? I did it once, but I cannot find it anymore.
0
votes
1answer
114 views

How to resolve “Circular dependency” in Microsoft Project

I am working in Microsoft Project for creating Low level plan in .mpp files. I am having the circular dependency error as shown in below snapshot: I want to know, is there any out-of-box ...
0
votes
2answers
821 views

Changing default working hours from 8 hr/day to 4 hr/day in Microsoft project 2013?

I am learning to use MS Project for a student project and trying to change the default working hours. I am not able to make this configuration change. How does one modify this setting? I tried ...
1
vote
1answer
98 views

Working with a pool/group of resources

How can I effectively work with a pool of team member (nor the usual resource pool share file in project)? Let me rephrase. My resources are spread into pools/groups, that share the same skills and ...
3
votes
3answers
195 views

Do you use the WBS or Project Program to structure tasks in MS Project?

When I first started using Microsoft Project, I took it for granted that I should replicate the WBS in the task list and use that to structure my work packages. After working with Project a little ...
5
votes
3answers
103 views

Level Remaining Resource Units

My goal is to optimize resource usage when having priority tasks partially allocated. MS Project 2007 simple two task scenario (My project has thousands of tasks) with automatic leveling: ...
0
votes
0answers
91 views

When a budget cost resource is assigned, the progress bar for the project summary task disappears

I'm using Microsoft Project Professional 2013 with Microsoft Project Server 2013. When a budget cost resource is assigned to the project summary task, the project summary task's progress bar ...
0
votes
1answer
131 views

Successor with Finish-to-start relationship starts at the same time as predecessor

When adding a task with a relationship Finish-to-Start, successor task starts at the same time as predecessor task. I have tried moving the task by dragging the second task, but then another problem ...
2
votes
1answer
460 views

Unable to schedule a 4-hour task completed over 2 days in Gantt Chart

I'm trying to create a detailed Gantt chart, using MS Project 2013, for a project in one of my courses. Being a student, I'm not working the same number of hours every day. For example, I may have a ...
0
votes
1answer
76 views

Scheduling tasks to start today

I have a plan that's broke up into a few stages. I want to schedule the first couple tasks in stage 2 to start as soon as possible, there are no predecessors for these tasks. My tasks in the middle of ...
1
vote
1answer
379 views

View project plan by week in a tabular format

There is a way to view your project plan in a table broken down by tasks ongoing in each week. I cannot for the life of me remember how to do this, and I'm not having any luck searching. Does anyone ...
0
votes
2answers
296 views

Let MS Project 2010 assign resources to tasks?

Technical question concerning MS Project 2010: I have a Gantt with a list of tasks. For each task I have the work defined (ex: 2 wks). Each task can only have one person (resource) assigned to it. ...
4
votes
3answers
637 views

Showing Microsoft Project files to people without Project

The project managers at my company were asked to use Microsoft Project 2013 to track our projects, but many of the business stakeholders do not have Project installed. It looks like I cannot just ...
0
votes
2answers
291 views

How to change the arrow icon which is displayed as the deadline indicator

Usually the Deadline icon is shown as arrow in the Gantt Chart. It is possible to change by right clicking and selecting format. Is it possible to show the deadline as a single line, just like ...
0
votes
1answer
141 views

How to permit multiple Project Managers to update a shared project

I have searched and not found an answer for this (nor did Google help). We are on Project Server 2007. I am running a large program with multiple project managers handling different parts of the ...
0
votes
2answers
513 views

Update project plan, rescheduling and dates

I'm trying to understand the update function in MS Project 2010 and I hope you can help. Let's say I have a road-project where I have divided a task in to several activities based on where the task ...
0
votes
2answers
285 views

How do I auto-level a project mid-duration taking into account % complete on tasks?

I have a MS Project 2007 plan with six months of work in it. I'm updating the % Work Complete on the tasks as we progress through the plan each week and month. I'm moving the "Project Start" date ...
0
votes
2answers
84 views

How do I create a task to obtain something with cost in MS Project?

I would like to setup a project that allows me to keep track of obtaining equipment for a business. Basically I the "progress" is the funds generated or the equipment obtained(e.g., if I stole it then ...
0
votes
2answers
336 views

MS Project 2010: Can I define an “overhead” task?

I have an "overhead" task for tracking work related to administration of a project. As such, the project requires about 5 hours of administrative overhead work per week of its existence. How can I ...
0
votes
1answer
1k views

MS Project how to compare “% Complete” with “Planned % Complete”

I need to have a column to show Planned % Complete for a certain date that I will compare with % Complete column. Now % Complete formula is cstr(IIf([Duration]=0,0,100*[Actual Duration]/[Duration])) ...
3
votes
6answers
3k views

Simple examples of the difference between fixed-work, fixed-unit, and fixed-duration tasks in MS Project

MS Project tasks are either fixed work, fixed unit, or fixed duration, where Duration x Units = Work The documentation describes which variable is recomputed when one of the others is changed, but ...
1
vote
2answers
2k views

MS Project: How to set a Resource work by hour regardless of work days?

Please kindly help me find way to solve in MS Project. I have two Resources below: Employee_A = 4 hours per week only, but can work any day Employee_B = 12 hours per week only, but can work any day ...
0
votes
1answer
216 views

Difference in %complete after rescheduling between MSP 2007 and 2010

I have a file that has a single task. its fixed duration and is not effort driven and no resource is defined. duration is set to 10 days. after 5 days, %complete is 10%. after entering this data and ...
0
votes
2answers
639 views

Example Gantt charts in proposals - how to remove dates in MS Project?

We are a B2B service provider. Many of our potential customers want to see a Gantt chart in the proposal. These are created based on a broadly estimated start date. Our problem: our clients aren't ...
3
votes
2answers
420 views

Getting estimated working time from MS Project

Our company has just recently started using MS Project Professional 2010 and we plan to eventually have a Project Server installation. I've created a few projects so far, but still claim to be a ...