For questions about identifying, documenting, communicating, or mitigating risks to a project's schedule.

learn more… | top users | synonyms

3
votes
3answers
114 views

How to do risk profiling?

I've recently started working on a data center migration project for a large financial services client. One of the tasks I'm accountable is risk profiling the migration based on the as-is and to-be ...
0
votes
3answers
168 views

How can I plan a project that has undefined scope associated with learning new skills?

The client has set (and we have agreed to) the deadline for a project. In order to complete the project, the team needs to master a new tool chain including Selenium and Java. How do I establish a ...
0
votes
2answers
142 views

How can we manage schedule risks brought into a project by 3rd party software?

Working in web-development, I face a common situation when clients want to use 3rd party software as a starting point of the project. That could be a CMS, an e-commerce site, or something else. ...
0
votes
4answers
719 views

How can I get inexperienced team members to meet project deadlines?

Recently, we have hired bunch of people who say they have little experience on technology. When I delegate jobs to them and ask for a timeline, they give unrealistic timelines of around 3-5 months. I ...
2
votes
5answers
169 views

Can story points remain constant between the initial estimate and later planning sessions?

Background We have a bunch of epic stories. We have a fixed term to do the project. We have to get approval from a project board. We don't know the velocity of the project team yet. The ...
3
votes
2answers
161 views

Who decides how much work should be included in each Sprint?

Once we have groomed the backlog and have a relatively clear direction of what should be done in short and long term, how do we decide what to include in each Sprint? Who makes that decision? It ...
2
votes
2answers
175 views

How should a drastic deviation in overall design be managed in Scrum?

We are starting a Sprint today, first day of a 3-week Sprint. Our requirements from the client are still evolving, so remaining hours are estimated on some unclear values. How should a deviation in ...
4
votes
4answers
262 views

Schedule Control

Here's the scenario: You are building a schedule for a project that has a planned duration about three months. You are not concerned about project costs so you will not be doing EV. You are ...
3
votes
4answers
241 views

What is a good way to set control limits on a schedule?

I want to try to track project progress using Earned Value Management approaches, mainly for my own education rather than out of a pressing need. The metric used to define planned value (PV) and ...
4
votes
7answers
596 views

Is planning software necessary?

Is planning software necessary? Can you plan your project without one?
3
votes
2answers
144 views

How to deal with inhouse technical group manager?

Regarding to management of a multi-task IT project; How to deal with technical group manager who risks the completion of the project in time by not respecting weekly work-schedule?
2
votes
2answers
204 views

Early stage risk/cost/time estimaties when working with unstable/beta software integration

What is the usual way to estimate costs in the first weeks of this kind of high risk projects where there is no specialist knowledge of the technologies you need to use in a development team? In my ...
8
votes
8answers
406 views

How can a PM prevent a train wreck in progress?

Our mid-size development team is doing a multi-year project. We always had major technical concerns that were never resolved. Now we find ourselves part of the way over a cliff: the architecture ...
3
votes
4answers
315 views

Would this be a good way of reporting?

I do not know whether I am reinventing the wheel, but I have never come across the following reporting method. I imagine that if I was to choose a single metric to report to upper management about a ...
1
vote
2answers
131 views

What is the Procedure For Handling High Risk Involving Another Team's Conflicting Goals?

I am working on an ongoing project which spans over the course of several years. The project has moved to the stage where the product we're building has customers. Our management structure is the ...
5
votes
5answers
3k views

How to calculate budget margin?

Say a work package (containing several tasks) is estimated to take between 320 (Most likely) and 480 (Worst case) hours of work (not duration) to complete. Because of some dependencies and the ...