Unanswered Questions

2
votes
7answers
211 views

Adding new tasks to the current baseline

I would like to ask what the best approach would be in the following scenario. I have a project with all the tasks. I've created the baseline but my boss comes and says: I need you to add these other ...
1
vote
0answers
32 views

How can I modify the Upland PowerSteering templates for Iterative/Agile Management?

Our department recently brought in Power Steering for waterfall projects but in the absence of an agile-focused software (Jira, Rally, VersionOne) there is some appetite to experiment with Power ...
1
vote
3answers
397 views

Factors to consider for Merging two or more IT Operations team into ONE

I believe this question falls under a Project from the Management side. But I would appreciate any help or resources for the scenario. The project as an IT Manager, is responsible for ...
0
votes
1answer
14 views

In Scrum, what is an impediment?

One of the questions in Scrum is What impediments have you encountered? But what exactly is an impediment? Can you give me an example?
0
votes
0answers
12 views

Documents to create prior to Kick-off Meeting

We have gotten approval of our Project Charter and have a kick-off meeting scheduled already and I'd like to know what documents do I need to create prior to this kick-off meeting and/or what ...
0
votes
1answer
16 views

How to reschedule activities after entering actuals in MS Project 2010

Like in MS Project 2007, there was a button “reschedule”. We clicked it after entering actuals on activities. The “reschedule” button calculates activity’s remaining duration and changes it ...
0
votes
0answers
9 views

Remaining work roll up value incorrect after refreshing TFS data in MS Project

I have problem importing TFS data into MS Project that is driving me crazy. When I first import TFS data into a new project all the roll up values for remaining work in MS Project are correct, but ...
0
votes
0answers
31 views

PERT adjust most likely time with probability and duration time

I don't know if the name of the question is clear what I would like to do is: I need to adjust the most likely time for an activity of my project in purpose of the probability of any path through the ...
0
votes
1answer
34 views

Duration of Recurring Tasks in MS Project

I have set up a recurring task to recur every 4 weeks for 4 occurrences. To me, this means the duration should be 4 x 4 x 7 = 112 days, but the duration is set to 253 days. Can someone explain?
0
votes
1answer
41 views

How to plan ahead your resource growth?

Several years ago I was in a startup and they explained to us about roadmap growth. That in the first year a startup should earn XXX money and the year after it should be YYY. the increment in money ...
0
votes
0answers
33 views

Master Project with Subprojects - need to share master but without the subprojects included

I have a master project which contains 11 sub projects. Whenever I send the master project to anyone, I have to send all the 11 sub project MPPs out to them too. Is there a way of creating the master ...
0
votes
1answer
42 views

TFS KanBan, How do you view total work done?

We have recently moved to the TFS KanBan boards and I am loving this organization. Breaking our stories up into smaller, more manageable tasks has been a huge help. We currently size in hours, and ...
0
votes
1answer
37 views

Tasks on my Project do not print

I am using MS Project at work, and I noticed on one job when i print the calendar, certain tasks do not show up. It appears that every task that is lower in the day cell does not show up on the Print. ...
0
votes
0answers
57 views

Resource usage total doesn't match Gantt chart total

I have an MS Project file where the total value of the effort calculated by adding up each resource in the Resource Usage sheet is greater than the total effort of the tasks in the Gantt chart. I've ...
0
votes
0answers
36 views

Estimating milling times for CNC milling moulds

I'm currently doing an internship for a tooling company. We make moulds for small plastic products out of aluminum, and my final thesis is supposed to be about projections (planning and costs) for ...

15 30 50 per page