Unanswered Questions

2
votes
6answers
130 views

Adding new tasks to the current baseline

I would like to ask what the best approach would be in the following scenario. I have a project with all the tasks. I've created the baseline but my boss comes and says: I need you to add these other ...
1
vote
3answers
327 views

Factors to consider for Merging two or more IT Operations team into ONE

I believe this question falls under a Project from the Management side. But I would appreciate any help or resources for the scenario. The project as an IT Manager, is responsible for ...
0
votes
0answers
6 views

Resource usage total doesn't match gantt chart total

Please help. I have an MS Project file where the total value of the effort calculated by adding up each resource in the Resource Usage sheet is GREATER than the total effort of the tasks in the Gantt ...
0
votes
1answer
19 views

Scheduling teams to complete a percentage of work

I'm trying to work out how to allocate work to different teams, and my brain is struggling with the logic. I have three different teams who arrive in a geographic area at different dates. There's a ...
0
votes
1answer
33 views

What is the definition of “development model”?

What is the definition of "development model"? For example: Waterfall model, Iterative model or Spiral model. In this case "model" is just synonym of "methodology" (wikipedia keep articles about ...
0
votes
0answers
21 views

Estimating milling times for CNC milling moulds

I'm currently doing an internship for a tooling company. We make moulds for small plastic products out of aluminum, and my final thesis is supposed to be about projections (planning and costs) for ...
0
votes
1answer
22 views

Microsoft Project, total resource usage by group

I have Project 365 and I am trying to create a view where a task will display all the resources it uses, and then total them by group. For example I have the Group "labour" where I've put all my ...
0
votes
2answers
38 views

How can I calculate required project resources with less manual computation?

My workflow process looks like this: I get some info about the number and complexity of project tasks. I have time-data about past tasks of the same complexity. I have prices for current tasks. I ...
0
votes
4answers
123 views

Estimate hours of work for every user story

In Scrum, is it mandatory to estimate the amount of hours needed to finish every user story before putting it in the Sprint? Or should we use planning poker and use points instead of hours?
0
votes
1answer
35 views

How to write a multi-point requirement for a requirements document?

I am a realtively new BA and I am having trouble finding the best way to write out a requirement that has multiple points. We are trying to build a dashboard, and I am getting conflicting opinions on ...
0
votes
1answer
48 views

How to divide work unevenly between resources in MS Project

I'd like to divide a task between resources at different usage levels to get the shortest duration for the task. For Example Task A : 80 hrs work Resource 1: 100% Resource 2: 50% I want this to ...
0
votes
1answer
49 views

Support for Resource Overview in Omniplan

In Omniplan 2.3.5, Is there any way to create a Resource report similar to the report Microsoft Project offers? This report should include: how many hours does a resource work when do they start ...
0
votes
2answers
88 views

Similarities / Differences between BPM and software projects

I have begun working for a company that resell BPM products, for improvement and automation, including small Sw development sometimes. Sadly, they have a colosal rate of failure when estimating time ...
0
votes
2answers
179 views

Agile resources for very short projects?

I'm having a job interview tomorrow with a group that typically has projects between 3-5 days in length. Of course, I'm not sure what exactly my duties will be, but I'm more used to projects around 2 ...
0
votes
1answer
103 views

How to work with different project management methods/tools in one org? Applying “Agile” in ops type work

In my role I need to manage two types of projects standard development projects (software/coding) operations related projects (IT/Vendors/Marketing - no coding involved) In the first one, we ...

15 30 50 per page