Unanswered Questions

2
votes
7answers
315 views

Adding new tasks to the current baseline

I would like to ask what the best approach would be in the following scenario. I have a project with all the tasks. I've created the baseline but my boss comes and says: I need you to add these other ...
1
vote
0answers
55 views

How can I modify the Upland PowerSteering templates for Iterative/Agile Management?

Our department recently brought in Power Steering for waterfall projects but in the absence of an agile-focused software (Jira, Rally, VersionOne) there is some appetite to experiment with Power ...
1
vote
3answers
456 views

Factors to consider for Merging two or more IT Operations team into ONE

I believe this question falls under a Project from the Management side. But I would appreciate any help or resources for the scenario. The project as an IT Manager, is responsible for ...
0
votes
1answer
13 views

How to atone for Fixed costs within MS Project which are based on duration?

I have successfully implemented fixed costs for a few of my tasks, one of them being accommodation cost which is a "one off" cost. However, how do I input fixed costs for tasks which rely on the ...
0
votes
0answers
25 views

In Asana is there a way to associate completed tasks with a release version?

I'm working mostly in Asana right now, and am hoping to find a way to associate completed tasks with a versioned cut of product (software in this case). Am I supposed to hack my workflow by creating ...
0
votes
2answers
25 views

MSProject: How to set up different resource availability for different workdays?

I need to set up a resource with the following availability in MS Project: Mon 50% Tue 50% Wed 100% Thu 50% Fri 0% Is this possible? Any help is greatly appreciated. Thank you Laszlo
0
votes
0answers
23 views

delay in schedule as KPI?

In Microsoft Project 2013, what is the best way to show delay in schedule as KPI? In EPM, I want to highlight the projects with more than 20% of schedule delay.
0
votes
1answer
25 views

How to display Time Tracking fields in Issue Detail View using Kanban Board in Jira?

That's it. How can I have Time Tracking fields (Original Estimate, Remaining Estimate) show up in Issue Detail View when using a Kanban Board (in "Work" mode) in Jira? Looks like this feature can ...
0
votes
2answers
65 views

Project Scope in Project Charter Vs 'Project Plan'

How is Project Scope different in 'Project Charter' different from Project Scope in 'Project Plan' considering they both have to be brief ... isn't it redundant ?
0
votes
0answers
65 views

MS Project: Percentage of elapsed work time of project

Suppose we have a project, that its progress is not going exactly on the plan (e.g. we have worked on some future tasks and some previous tasks are not completed on the schedule). and also some ...
0
votes
1answer
52 views

Summary task in MS Project displaying as task on Gantt chart

I've set some simple color formatting up to distinguish late, completed and future planned tasks on a project plan in MS project for ease of use for sponsors who just want to glance at the plan. The ...
0
votes
0answers
22 views

Remaining work roll up value incorrect after refreshing TFS data in MS Project

I have problem importing TFS data into MS Project that is driving me crazy. When I first import TFS data into a new project all the roll up values for remaining work in MS Project are correct, but ...
0
votes
0answers
53 views

PERT adjust most likely time with probability and duration time

I don't know if the name of the question is clear what I would like to do is: I need to adjust the most likely time for an activity of my project in purpose of the probability of any path through the ...
0
votes
1answer
63 views

Master Project with Subprojects - need to share master but without the subprojects included

I have a master project which contains 11 sub projects. Whenever I send the master project to anyone, I have to send all the 11 sub project MPPs out to them too. Is there a way of creating the master ...
0
votes
1answer
52 views

Tasks on my Project do not print

I am using MS Project at work, and I noticed on one job when i print the calendar, certain tasks do not show up. It appears that every task that is lower in the day cell does not show up on the Print. ...

15 30 50 per page