Unanswered Questions

2
votes
2answers
54 views

Planning in MS Project: fixed work AND fixed duration

I currently plan a quite complex project in MS Project. At the moment I cannot plan everything out in detail, but I think that in my head I have a good understanding of how long a task will last and ...
1
vote
1answer
36 views

Separation of cost from percentage complete?

I am monitoring the progression of a mine shaft. I have 2 goals each month: Goal 1: Progress 247 feet per month Goal 2: Spend roughly $133k per month. However, spend is not solely driven by the ...
1
vote
1answer
44 views

Microsoft Project Task to Start and Finish on the Same Day?

I have a project with a number of similar tasks all with slightly different durations. The tasks are also broken down into sub-tasks (all the sub-tasks are the same for each main task, again only ...
1
vote
3answers
73 views

In Asana is there a way to associate completed tasks with a release version?

I'm working mostly in Asana right now, and am hoping to find a way to associate completed tasks with a versioned cut of product (software in this case). Am I supposed to hack my workflow by creating ...
1
vote
0answers
88 views

How can I modify the Upland PowerSteering templates for Iterative/Agile Management?

Our department recently brought in Power Steering for waterfall projects but in the absence of an agile-focused software (Jira, Rally, VersionOne) there is some appetite to experiment with Power ...
1
vote
1answer
123 views

Tasks on my Project do not print

I am using MS Project at work, and I noticed on one job when i print the calendar, certain tasks do not show up. It appears that every task that is lower in the day cell does not show up on the Print. ...
1
vote
4answers
583 views

Factors to consider for Merging two or more IT Operations team into ONE

I believe this question falls under a Project from the Management side. But I would appreciate any help or resources for the scenario. The project as an IT Manager, is responsible for ...
0
votes
1answer
9 views

Question about documenting project hours on PMP application

I've been working in a PMO since July of 2013. I estimate that I have roughly 3520 hours of project hours from working there. I got this estimate by counting 22 months between then and now and ...
0
votes
0answers
18 views

How are items with dependencies to other items handled in Kanban?

In our team we are working with system integration testing only. This means that we don't have any development tasks, just testing tasks and tasks related to preparing our heavy systems for test. We ...
0
votes
0answers
27 views

objectives and release train philosophy

I have a question about this article "The Role of PI Objectives" (https://www.rallydev.com/community/coaching/role-pi-objectives), where the author stated near the end of the article: "As I captured ...
0
votes
0answers
17 views

Any tips for customizing a Kanban View for Outlook Tasks?

I worked out how to create a Kanban View in Outlook, at last, and had hoped to contribute to this excellent and inspirational thread at "Where to Find a Desktop Kanban board application?", but I ...
0
votes
2answers
31 views

Using TFS 2013 for Portfolio Management

1)I am planning on setting up TFS 2013 and using TFS 2013 for managing a number of projects, using the Portfolio Management features. I wanted to get a general opinion if this is a good idea - or is ...
0
votes
1answer
38 views

How to add milestone in MS Project server 2013?

I have MS Project server 2013 integrated with SharePoint 2013. I have created PWA site and in task page I want to add milestone as we do in MS Project professional 2013 but I don't see any options, ...
0
votes
1answer
37 views

Project task list to move some server to new data center?

Actually we just completed the installation and fully equipped with new technology equipments for new data center's room. We are considering to move some sever to that location, are you aware of any ...
0
votes
1answer
25 views

How much detail should the solution design have in Foundations in DSDM?

In the DSDM Atern Life cycle, here. In the foundation phase it states one of the objectives is to: To start designing the solution architecture and identifying the physical or infrastructural ...

15 30 50 per page