Unanswered Questions

2
votes
0answers
79 views

How can we adopt Kanban to our workflow?

I'm working in a creative agency, with 8 people sharing the same physical space. Some of us travel often, and we are loosely organized in the following departments: RnD, Design, Social, and ...
2
votes
6answers
132 views

Adding new tasks to the current baseline

I would like to ask what the best approach would be in the following scenario. I have a project with all the tasks. I've created the baseline but my boss comes and says: I need you to add these other ...
1
vote
3answers
332 views

Factors to consider for Merging two or more IT Operations team into ONE

I believe this question falls under a Project from the Management side. But I would appreciate any help or resources for the scenario. The project as an IT Manager, is responsible for ...
0
votes
0answers
4 views

Tasks on my Project do not print

I am using MS Project at work, and I noticed on one job when i print the calendar, certain tasks do not show up. It appears that every task that is lower in the day cell does not show up on the Print. ...
0
votes
0answers
18 views

Tracking external events during lifetime of a software project in production use?

What tool(s) could be used to track various external events during lifetime of a software project in production use? Say, expiration dates of hardware support contracts, software licenses, domain ...
0
votes
1answer
22 views

Resource usage total doesn't match Gantt chart total

I have an MS Project file where the total value of the effort calculated by adding up each resource in the Resource Usage sheet is greater than the total effort of the tasks in the Gantt chart. I've ...
0
votes
1answer
40 views

What is the definition of “development model”?

What is the definition of "development model"? For example: Waterfall model, Iterative model or Spiral model. In this case "model" is just synonym of "methodology" (wikipedia keep articles about ...
0
votes
0answers
23 views

Estimating milling times for CNC milling moulds

I'm currently doing an internship for a tooling company. We make moulds for small plastic products out of aluminum, and my final thesis is supposed to be about projections (planning and costs) for ...
0
votes
1answer
23 views

Microsoft Project, total resource usage by group

I have Project 365 and I am trying to create a view where a task will display all the resources it uses, and then total them by group. For example I have the Group "labour" where I've put all my ...
0
votes
2answers
39 views

How can I calculate required project resources with less manual computation?

My workflow process looks like this: I get some info about the number and complexity of project tasks. I have time-data about past tasks of the same complexity. I have prices for current tasks. I ...
0
votes
4answers
126 views

Estimate hours of work for every user story

In Scrum, is it mandatory to estimate the amount of hours needed to finish every user story before putting it in the Sprint? Or should we use planning poker and use points instead of hours?
0
votes
1answer
44 views

How to write a multi-point requirement for a requirements document?

I am a realtively new BA and I am having trouble finding the best way to write out a requirement that has multiple points. We are trying to build a dashboard, and I am getting conflicting opinions on ...
0
votes
1answer
48 views

How to divide work unevenly between resources in MS Project

I'd like to divide a task between resources at different usage levels to get the shortest duration for the task. For Example Task A : 80 hrs work Resource 1: 100% Resource 2: 50% I want this to ...
0
votes
1answer
49 views

Support for Resource Overview in Omniplan

In Omniplan 2.3.5, Is there any way to create a Resource report similar to the report Microsoft Project offers? This report should include: how many hours does a resource work when do they start ...
0
votes
2answers
88 views

Similarities / Differences between BPM and software projects

I have begun working for a company that resell BPM products, for improvement and automation, including small Sw development sometimes. Sadly, they have a colosal rate of failure when estimating time ...

15 30 50 per page