Unanswered Questions

4
votes
1answer
596 views

How to permit multiple Project Managers to update a shared project

I have searched and not found an answer for this (nor did Google help). We are on Project Server 2007. I am running a large program with multiple project managers handling different parts of the ...
3
votes
1answer
85 views

How can I suppress task type indicators for “The task has a calendar applied to it.”

In an mpp file the owner has set a certain calendar and therefore that calendar setting is shown for every single task in the Indicators column. Is it possible to exclude some indicators from being ...
3
votes
4answers
240 views

PM communication model

In our search for a zero-email SE/BIM solution, we’re struggling to strip communication ‘terms’ to their essence. In PM-jargon, we tend to use many terms, such as; Decision - Action - Task - Note - ...
3
votes
1answer
183 views

Calendar Day Column

I need to set up a column that displays calendar days so that the project team can see the overall duration in addition to the working days. When I use the DateDiff("d",[Start],[Finish]) formula it ...
2
votes
3answers
95 views

How to create a visual product road map that follows agile?

My boss loves Gaant charts, because they give you a high level visual overview of the product roadmap. The problem with Gaant, it is fixed time related and goes completely against the concept of the ...
2
votes
1answer
93 views

What would a better industry standard title be than “Team Captain” and “Team Leader”?

I recently took a position as a Team Captain. I report to my Team Leader who then reports out of department to an operations manager who manages multiple departments with hundreds of people. I handle ...
2
votes
1answer
51 views

MS Project 2013 - Resource Overallocations during specific time period with 100% Availability

Is there a way to set resource availability by task (not project) during a specific time period in MS Project 2013 ? For example there is a resource allocated to Task 1 that starts in Dec 2015 and ...
2
votes
0answers
107 views

In TaskJuggler, how to manage multiple projects running in parallel

I manage three different projects with TaskJuggler. These project share some of the resources. I follow these suggestions and created three different .tjp files. I'm fine for my individual reports, ...
2
votes
1answer
121 views

Actual Start Date Field Behavior

Entering an Actual Start that is earlier than the Scheduled Start, say by 1 hour, is adding the 1 hour to the duration field instead of decrementing the finish date by 1 hour.
2
votes
1answer
167 views

Objectives and release train philosophy

I have a question about this article "The Role of PI Objectives", where the author stated near the end of the article: As I captured these thoughts I was reminded of a key difference between ...
1
vote
2answers
81 views

What are the benefits of PRINCE2 Agile?

I have recently heard about a new methodology that mixes PRINCE2 and Agile called PRINCE2 Agile. I was wondering what could be the benefits and reasoning behind this? As I understand PRINCE2 is a ...
1
vote
1answer
60 views

Am I implementing scrum properly?

First time doing this, seems to be working well. I am currently the Product manager/Scrum master, I have a team of 2 developers and a QA tester. Product is organised in the following way: Weekly ...
1
vote
2answers
34 views

Planning a release around the Apple's AppStore in mind

I am currently working for a company that has adopted scrum and we are trying to figure a rule for how to account for tech support, bug fixing and the unknowns of the Apple appstore within our ...
1
vote
1answer
31 views

One channel per task to track all discussions related to particular tasks in Slack: good or bad idea?

Wanting to quickly see everything that has been said regarding a particular task is very common. And often impossible, because both channels and PM contain discussions about multiple tasks. Therefore, ...
1
vote
1answer
38 views

Leveling Doesn't Work on Overallocated Resources in Project 2010

I have two simultaneous tasks and the same resource assigned to them, which naturally produced an overallocation in MS Project 2010. The leveling tools on the Resource tab, for some reason, are not ...

15 30 50 per page