Unanswered Questions

3
votes
4answers
42 views

What level of analysis should the development team expect before being asked to estimate and develop a story?

First of all, please excuse the rather lengthy question but I thought an example would be helpful. In my current role I am working as a developer in an agile team. Here is an example of s story ...
1
vote
2answers
49 views

In Asana is there a way to associate completed tasks with a release version?

I'm working mostly in Asana right now, and am hoping to find a way to associate completed tasks with a versioned cut of product (software in this case). Am I supposed to hack my workflow by creating ...
1
vote
0answers
59 views

How can I modify the Upland PowerSteering templates for Iterative/Agile Management?

Our department recently brought in Power Steering for waterfall projects but in the absence of an agile-focused software (Jira, Rally, VersionOne) there is some appetite to experiment with Power ...
1
vote
1answer
71 views

Tasks on my Project do not print

I am using MS Project at work, and I noticed on one job when i print the calendar, certain tasks do not show up. It appears that every task that is lower in the day cell does not show up on the Print. ...
1
vote
3answers
479 views

Factors to consider for Merging two or more IT Operations team into ONE

I believe this question falls under a Project from the Management side. But I would appreciate any help or resources for the scenario. The project as an IT Manager, is responsible for ...
0
votes
0answers
3 views

MS Project Predecessor Path in Gantt Chart

In MS Project 2010, is it possible to show the entire predecessor path driving the start of one specific task in a Gantt Chart?
0
votes
0answers
10 views

Missing topics & weaknesses in PMP Head first

One of best books in PMP is headfirst, it is helping you to understand PMP like story but i found uncovered topics on it -found in RITA book- like : Present value (integration knowledge area) ...
0
votes
0answers
26 views

task duration not coming correct as per start and finish dates

i am using MSP 2010. there is a problem which i never faced before. if i set a duration of a task as 10 days, the dates should be reflected accordingly. but it does not. Work order issue to vendors ...
0
votes
1answer
56 views

Kurt Lewin's 3 stage change process: which stage has the most resistance?

Is there in Kurt Lewin's 3 stage change process (Wiki) any "resistance distribution" or all stages have nearly equal resistance level? If so, which stage actually has the most resistance level?
0
votes
2answers
39 views

Edit the wbs column in microsoft project / import wbs + indent tasks

I sometimes use Freemind in the early startup process of projects for brainstorming with the project team. With freemind, it is possible to save the mindmap as an ODT file which then creates a WBS for ...
0
votes
0answers
30 views

When was the PMI ACP Exam last updated?

All - Has the PMI-ACP exam been updated since January 31, 2012? I am preparing to begin studying for the exam and I am planning to use "PMI-ACP Exam Prep" from Mike Griffiths and the front cover ...
0
votes
1answer
25 views

How to atone for Fixed costs within MS Project which are based on duration?

I have successfully implemented fixed costs for a few of my tasks, one of them being accommodation cost which is a "one off" cost. However, how do I input fixed costs for tasks which rely on the ...
0
votes
2answers
58 views

MSProject: How to set up different resource availability for different workdays?

I need to set up a resource with the following availability in MS Project: Mon 50% Tue 50% Wed 100% Thu 50% Fri 0% Is this possible? Any help is greatly appreciated. Thank you Laszlo
0
votes
0answers
90 views

MS Project: Percentage of elapsed work time of project

Suppose we have a project, that its progress is not going exactly on the plan (e.g. we have worked on some future tasks and some previous tasks are not completed on the schedule). and also some ...
0
votes
1answer
89 views

Summary task in MS Project displaying as task on Gantt chart

I've set some simple color formatting up to distinguish late, completed and future planned tasks on a project plan in MS project for ease of use for sponsors who just want to glance at the plan. The ...

15 30 50 per page