Timeline for FixedPrice but customer wants all risks are handled by their side
Current License: CC BY-SA 3.0
3 events
when toggle format | what | by | license | comment | |
---|---|---|---|---|---|
Jan 3, 2014 at 2:25 | comment | added | David Espina | Change request process should ALWAYS be strict, no matter the type of contract. In my opinion, just avoid this set up and simply go with a T&M or CP. That's what they're asking for, really. To be in some control of the costs. | |
Jan 2, 2014 at 21:33 | comment | added | Ruslan | That is what I'm thinking about as well. Is there any approach how vendor could save themselves ? for example any strict approach about change requests ? or maybe FP but instead of one project couple of smaller ones ? | |
Jan 2, 2014 at 20:36 | history | answered | David Espina | CC BY-SA 3.0 |