Software Version:Version: Microsoft Project 2013 Standard (15.0.4420.1017)

Hello -

I am creating a report in MS Project 2013. When I create a time-phased line chart containing ACWP, the ACWP shown in the chart for the current status date does not match the ACWP shown in a table (same status date) or in a column chart within the same report. The table and the column chart show $10,401.45, while the line chart shows $90,401.45. Images provided below for reference. Also for reference - the ACWP shown in the report's tabular view exactly matches the ACWP shown in the Earned Value table in Project's Gantt chart view.

ACWP for 9/8/2014

enter image description here

(Matches values shown in Gantt view and in a column chart in the report.)

enter image description here

enter image description here

enter image description here

The difference between the two ACWP values is exactly $80,000. This precisely matches the value of a specific task in the schedule that is set up as a milestone and has no associated hours, but DOES have a cost resource assigned with an $80,000 cost. I am not certain why the chart is picking up this additional $80,000 when the tables do not show it. (Also note that when I export the data to Excel using "Visual Reports," the $80,000 task is not included in the exported ACWP.

Any idea why I am seeing this seeming inconsistency?

Thanks!

Software Version: Microsoft Project 2013 Standard (15.0.4420.1017)

Hello -

I am creating a report in MS Project 2013. When I create a time-phased line chart containing ACWP, the ACWP shown in the chart for the current status date does not match the ACWP shown in a table (same status date) or in a column chart within the same report. The table and the column chart show $10,401.45, while the line chart shows $90,401.45. Images provided below for reference. Also for reference - the ACWP shown in the report's tabular view exactly matches the ACWP shown in the Earned Value table in Project's Gantt chart view.

ACWP for 9/8/2014

enter image description here

(Matches values shown in Gantt view and in a column chart in the report.)

enter image description here

enter image description here

enter image description here

The difference between the two ACWP values is exactly $80,000. This precisely matches the value of a specific task in the schedule that is set up as a milestone and has no associated hours, but DOES have a cost resource assigned with an $80,000 cost. I am not certain why the chart is picking up this additional $80,000 when the tables do not show it. (Also note that when I export the data to Excel using "Visual Reports," the $80,000 task is not included in the exported ACWP.

Any idea why I am seeing this seeming inconsistency?

Thanks!

Version: Microsoft Project 2013 Standard (15.0.4420.1017)

Hello -

I am creating a report in MS Project 2013. When I create a time-phased line chart containing ACWP, the ACWP shown in the chart for the current status date does not match the ACWP shown in a table (same status date) or in a column chart within the same report. The table and the column chart show $10,401.45, while the line chart shows $90,401.45. Images provided below for reference. Also for reference - the ACWP shown in the report's tabular view exactly matches the ACWP shown in the Earned Value table in Project's Gantt chart view.

ACWP for 9/8/2014

enter image description here

(Matches values shown in Gantt view and in a column chart in the report.)

enter image description here

enter image description here

enter image description here

The difference between the two ACWP values is exactly $80,000. This precisely matches the value of a specific task in the schedule that is set up as a milestone and has no associated hours, but DOES have a cost resource assigned with an $80,000 cost. I am not certain why the chart is picking up this additional $80,000 when the tables do not show it. (Also note that when I export the data to Excel using "Visual Reports," the $80,000 task is not included in the exported ACWP.

Any idea why I am seeing this seeming inconsistency?

Thanks!

2 edited tags
| link
    Tweeted twitter.com/#!/StackProjects/status/513436302495080448
1
source | link

MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table

Software Version: Microsoft Project 2013 Standard (15.0.4420.1017)

Hello -

I am creating a report in MS Project 2013. When I create a time-phased line chart containing ACWP, the ACWP shown in the chart for the current status date does not match the ACWP shown in a table (same status date) or in a column chart within the same report. The table and the column chart show $10,401.45, while the line chart shows $90,401.45. Images provided below for reference. Also for reference - the ACWP shown in the report's tabular view exactly matches the ACWP shown in the Earned Value table in Project's Gantt chart view.

ACWP for 9/8/2014

enter image description here

(Matches values shown in Gantt view and in a column chart in the report.)

enter image description here

enter image description here

enter image description here

The difference between the two ACWP values is exactly $80,000. This precisely matches the value of a specific task in the schedule that is set up as a milestone and has no associated hours, but DOES have a cost resource assigned with an $80,000 cost. I am not certain why the chart is picking up this additional $80,000 when the tables do not show it. (Also note that when I export the data to Excel using "Visual Reports," the $80,000 task is not included in the exported ACWP.

Any idea why I am seeing this seeming inconsistency?