Feb 1, 2017 at 6:04 | comment | added | Luc Pavot | @bobo2000 I'm glad it worked out :) | |
Jan 31, 2017 at 9:28 | comment | added | bobo2000 | @LucPavot created and showed my boss the product roadmap in this format, he was very happy. Thank you Luc! | |
Jan 29, 2017 at 20:27 | comment | added | João Farias | Remember that who says what is priority is the Product Owner. You can help him, give him a start point, but if can't let him just approve the document and never look at it again for a long time. You will probably something that he does not want/need and make him loses tons of money. | |
Jan 27, 2017 at 17:50 | comment | added | bobo2000 | Has your stakeholder found having a product roadmap in that format helpful? | |
Jan 27, 2017 at 9:41 | vote | accept | bobo2000 | ||
Jan 27, 2017 at 5:56 | comment | added | Luc Pavot | Yes we did, this overall roadmap doesn't change much, sometimes we need to re-calibrate and extends the work on a module of one month but that's it. The micro plan using a gantt chart is the one changing weekly depending of the progress on each task. | |
Jan 26, 2017 at 11:28 | comment | added | bobo2000 | Did you build it? Do you find that the product roadmap often changes | |
Jan 26, 2017 at 6:58 | comment | added | Luc Pavot | That's just a spreadsheet used graphically. Not usually recommended but it served my purpose. | |
Jan 25, 2017 at 9:02 | comment | added | bobo2000 | How did you create that ? | |
Jan 25, 2017 at 6:01 | history | answered | Luc Pavot | CC BY-SA 3.0 |