Dec 6, 2019 at 8:57 comment added Bogdan Prescribed means it's recommended to use because they have proven to be useful. Burndowns are not Scrum artifacts as per the definition of the guide (although because of their usefulness you might be tempted to stretch the definition of what the word "artifact" means), but Scrum prescribes them to monitor progress towards goals (see the "Monitoring Progress Toward Goals" section in the Scrum Guide)
Dec 6, 2019 at 8:49 history edited Bogdan CC BY-SA 4.0
added 312 characters in body
Dec 6, 2019 at 7:57 comment added Seeker001 scrumguides.org/scrum-guide.html
Dec 6, 2019 at 7:17 comment added Seeker001 How is Burndown chart prescribed in Scrum if in Scrum Guidebook there are only 3 artifacts? Product backlog, Sprint Backlog, and Increment. I don't believe a Burndown chart was mentioned.