Timeline for How do you maintain proper resource leveling in MS Project after baseline since resource leveling shifts to maintain slack+leveling days?
Current License: CC BY-SA 4.0
3 events
when toggle format | what | by | license | comment | |
---|---|---|---|---|---|
Aug 5, 2020 at 13:14 | comment | added | David Espina | @TomBoyle, the five days between A and B was due to the leveling delay? I avoid using the auto leveling function. Will you provide an answer as to what is occurring here? | |
Aug 5, 2020 at 13:09 | comment | added | Tom Boyle | Task B has a 5ed leveling delay, not a lag. Leveling delays are normally applied, adjusted, and otherwise managed by the resource leveling engine, but it appears here that the OP has entered it directly. Once entered, of course, the leveling delay looks a lot like a lag (on the forward pass.) | |
Aug 5, 2020 at 12:56 | history | answered | David Espina | CC BY-SA 4.0 |