I have a plan in MS Project. I have a resource that can't work 5 days per week, so I have negotiated with him to work just 3 days per week. In the plan, I changed his calendar for Thursday and Friday to be non-working days.
When a 12-hour task starts on Wednesday and finishes Monday, MS Project shows the task with 28 hours duration. How can I get MS Project to calculate this as 12 hours?