I have kept the correct start and end date but the duration is getting wrongly calculated.
The start date is 11-June-2015 and end date is 16th -Sept -2015 . They are appearing fine in MPP. But the duration is showing as 291 days which is clearly more than the difference between the start and end dates.
The durations at task level is appearing fine but the overall project level duration appears to be wrong.
Any suggestions?