How to set Undo Level of MS project 2010 by the help of Visual Basic.

I set by option> Advanced>Undo Level but it's not working properly. How to find VB code window for set the undo level in MS project 2010.

1 Answer 1

1

The property is UndoLevels. For example: Application.UndoLevels = 10 set the number of undo levels to 10.