1

I have a task that has two people working at 80% of their time on it. I have entered a task with work = 3 days. I expect the duration to be 3 / (2 x 0.8) = 1.88 days. But project insists that it is 3.05 days. I have this for a lot of other tasks in a project.

The task not effort driven and is in fixed units.

I really don't understand this. Can someone explain.

1
  • 1
    Make the task effort driven – David Espina Oct 20 '13 at 13:29
2

I assume when you say the work is 3 days - you are saying 24 hours of work. Each resource should be performing half of the work - 12 hours.

You have a couple of options to have Project calculate the correct duration:

  1. In the Task Form, enter 12 hours of work for each resource. Project will correctly calculate the duration based upon Work/assignment units.
  2. Remove the second resource, ensure the task is effort driven. Re-assign the second resource and Project will divide the 24 hours of work evenly - 12 hours for each resource - and re-calculate the correct duration.

If you wish Project to divide work between assigned resources, ensure your task types are effort driven and assign each resource separately.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.