We are using MS Project 2010 to manage our projects. We have a subcontractor that works on the same project. They report differently within their company than we do.
So, we had him break apart his schedule so that we could bring them in as four small chunks in the appropriate places in our schedule. The problem is that no matter what % complete the subcontractor schedules report, it does not impact the overall % complete.
This seems incredibly counterintuitive. How should we fix this issue? Is it even an issue at all? If not, how do we handle this?