I am using MS Project 2010. My Task Type is defined as Fixed Work. I have tried Fixed Duration and it only seemed to make the matter worse.
I have a task that spans 10 days (2 weeks). However, the task is only estimated to take 20 hours. At the end of the first week 13 hours of work was completed. Although there is still another full week to complete the remaining 7 hours of work MS Project changed the Finish Date on the task, adding one day to it.
Why? How can I prevent this from happening?