2

If you're NOT paying for software like Jira, what/how do you create your own burn-down charts?

I have seen a few tools out there for creating burn-down charts. The one I'm most familiar with is setting up a template in Excel and working that way. I've also seen third-party add on's for Chrome and Trello.

2
2

The best tool, though you could argue about the free part, for me is a whiteboard or flip chart and a marker. Though any sheet of paper and pen will do.

It's easy to implement, too. Just put numbers on your cards, draw the two axes and you're set.

Start from there and get your process on order first. Once you and your team have established your own flavor of scrum, you will know what your requirements are and screening tools will be a quick exercise, but not knowing what the tool is supposed to do, flexibility is key. And not much can beat board and marker in that respect.

Source: my own experience building and coaching scrum teams

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.