0

I need to have a column to show Planned % Complete for a certain date that I will compare with % Complete column.

Now % Complete formula is

cstr(IIf([Duration]=0,0,100*[Actual Duration]/[Duration])) & " %"

customize Planned % Complete formula that I make is

cstr(IIf([Duration]=0,0,100*ProjDateDiff([Start],[Status Date])/[Duration])) & " %"

both formulae give me exactly same result but at task level only. However, the later one does not give correct result at summary level if I use use formula for roll-up.

I am really struggling with this, would appreciate your help. Or should I entirely follow different approach.

  • To work out the planned % complete surely you need to work that out from a baseline? Looking at current stats will only represent the current position surely? – Marv Mills Dec 23 '13 at 13:18
1

First, using duration to calculate % complete is unreliable. Physical percent complete is a better, more precise method. Second, use earned value. Cost, schedule, and finish variances inherent in EV methods are already built into MS Project, though a little clugy. But, you don't have to make up new formulas.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.