I have a plan that's broke up into a few stages. I want to schedule the first couple tasks in stage 2 to start as soon as possible, there are no predecessors for these tasks. My tasks in the middle of stage two are dependent upon the completion of tasks from stage 1 and the first tasks of stage 2, so those scheduled start dates are driven and being updated from the work in stage 1.
My plan was created months ago and my tasks at the start of stage 2 have still not been started for reasons outside the project. So now my scheduled start dates still have 2013 dates for those tasks and its now February.
Is there a way to have Microsoft Project 2010 adjust the scheduled start dates for tasks that have not started yet to be "today" for tasks that have no predecessors and can start as soon as possible. I'm trying to avoid updating the tasks to "start no earlier than" and manually updating those dates each time I update the plan.