I'd like to divide a task between resources at different usage levels to get the shortest duration for the task. For Example
Task A : 80 hrs work Resource 1: 100% Resource 2: 50%
I want this to result in something like 7 days duration: Resource 1 = 54 hours, Resource 2 = 26 hours
Instead...
MS project divides the work evenly between the two resources and completes the task based on the slowest (least utilized) resource: 10 day with 40 hours each for resource 1 and 2. Thus resource 1 stops working once they've done their 40 hours
How do I get MS project to keep all resources working at their maximum rate until a task is complete?