Say I have a process taking 19 h. Some improvement measures allow to reduce the required time to 17 h (to reach the same level of output).

Does it make sense to say that the process is now (1-17/19)*100 ~= 10% more efficient?

If not, what kind of quantification of the process improvement would make sense?

1

Many Paths to Process Improvement

Processes can be improved in a variety of ways:

  • Speed.
  • Quality.
  • Cost.
  • Cycle time.
  • Lead time.

and probably tons of other dimensions, too. If your process is repeatably two hours faster, rather than a statistical outlier, then you could certainly say your new-and-improved process is 10.5% faster than before, but it may or may not be more 10.5% more efficient.

Speed <> Efficiency

Whether or not your process is actually more efficient depends on how you choose to interpret efficiency and what you want to get out of an optimized process. Consider these examples.

  • If your process is 2 hours faster because you've added another person to the team, is that more efficient?
  • If your process is 2 hours faster, but has an increased defect rate, is it more efficient?
  • If your process is 2 hours faster but requires more fuel per widget produced, is it more efficient?

These aren't trick questions. The answer is just as likely to be yes as it is no, because for most organizations "efficiency" is a buzzword that's really a proxy for something else. In my own experience, it's most often a proxy for value/time or value/cost, but an engine manufacturer might think an improvement in the rate of energy capture is what the process ought to be optimized for.

Unlike some of the hard sciences, efficiency is a less objective term in project management. Therefore, your mileage will vary.

| improve this answer | |
  • +1 for linking the 2. law. And I can see your point. I guess my understanding of "efficiency" is currently a bit cloudy. – TMOTTM Sep 27 '14 at 6:42
0

I would call that a 10% savings of time. But time is only one factor of efficiency. To look at the efficiency savings you need to capture the ratio of output/input of the before and output/input of the after and compare the delta.

| improve this answer | |
  • And maybe also the ration of resource / workforce usage? It makes a lot of difference if the process takes 10% less time but 20% more raw materials / energy / employees to complete. – Péter Török Sep 26 '14 at 8:56
0

In Lean, there is a Process Cycle Efficiency metric calculated as a ratio between cycle time and value-added time. From the 17h how much of it was valuable effort? For example: 5h (value-added time) / 17h (cycle time) = 30% (process efficiency).

| improve this answer | |