I have a number of summary tasks consisting of 4 or 5 subtasks (max 4 days each). These subtasks have dependencies, but the different summary tasks are not dependent on each other. The subtasks are performed by different persons.
When I scedule this in Project, the summary tasks scedule themselves on a long stretch taking up to 100 days per summary task, because some persons are available way sooner than others. Without wanting to set a 'start no earlier than' dependency, how can I set the summary tasks at a maximum of 20 days each? When I enter 20 days at the summary task it has allocation problems. As it does not rescedule the subtasks.