0

How can Critical Chain as a scheduling approach be applied using only Microsoft Project 2010 with no add-ins or additional software? What settings and options need to be used, and what task types.

2

Sorry, Project does not use critical chain methodology - only critical path. There are add ins (ProChain for example) but not native to the product.

  • That's what I suspected. Is there any suggested customisations, VBA or work arounds though? A third party add-in is not an option for my organisation. – Adrian Davis Jan 7 '15 at 12:50
  • 1
    If you use your favorite search engine and search for Agile in Microsoft Project, you'll see a variety of resources ranging from YouTube videos. Here's a link to the MS project webcasts. Take a look at Tim Runcie's webcast from Dec 2013. blogs.office.com/2013/08/12/microsoft-project-webcast-series – JulieS Jan 7 '15 at 21:07
  • its a pain to register too but the webcast was helpful, thankyou – Adrian Davis Jan 13 '15 at 15:54
  • You're welcome. Glad you found it helpful. – JulieS Jan 13 '15 at 17:13

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.