0

Is it possible to force a re-calculation of a the "Work" field after updating % allocation of resources in the resource sheet or in the resource names column?

I am using MSP 2013 standard.

| improve this question | | | | |
1

I'm guessing you mean to re-assign resources at a different assignment units after you change the resource's max units?

If so, not automatically. However, you can quickly replace resources with the same resources at a different assignment value.

  1. If the Project summary task is visible, turn it off by clearing the check from the "Project Summary Task" option on the Format Ribbon.
  2. Select all tasks in the file by selecting the Task Name column heading.
  3. Select Assign Resources on the Resource Ribbon and select the resource you need to change in the list.
  4. Click Replace.
  5. Select the same resource and Manually enter the new assignment units.
  6. Click OK in the Replace Resources dialog.
  7. Repeat as needed with other resources.
| improve this answer | | | | |
0

No.

For tasks designated as Fixed Units, once there is a value for Work and a value for Duration, MS-Project cannot tell whether you want to keep work the same and adjust duration, or keep duration the same and adjust work.

You could try designating the tasks as either Fixed Work or Fixed Duration, depending on your local needs...

| improve this answer | | | | |

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.