1

As far as I understand during the sprint planning meeting the team choose the backlog items that will be included in the sprint.

How formal is the sprint planning and task assignments? Once the sprint starts is normal to use PMBOK artifacts such as a project charter and a WBS to guide the sprint or the development team decide what to do on the go?

P.D. I only have a basic knowledge of scrum. I would like to apologize in advance if I am constructing this question wrong!

2 Answers 2

3

Sprint planning is a meeting held between the Product Owner and the team doing the work. The Product Owner is the one that prioritises the backlog and also briefs the team on the items at the top of the backlog.

The team then estimates the backlog items and because it knows its typical sprint capacity (i.e. its velocity) it decides how far down the backlog it can go. For example, it might have a velocity of 20 points and so would select the items prioritised by the Product Owner down to the point where they had roughly 20 points allocated.

Scrum doesn't really prescribe much beyond that point up until the end of the sprint and the sprint review. Its up to the team and the Product Owner to agree on how they will work.

With most teams the process would be as follows. The team would work on the items allocated to the sprint, roughly following the prioritisation used by the Product Owner. They may vary the order a bit from the Product Owner's priorities for technical reasons. All along there would be constant communication between the team and the Product Owner. The team would ask frequent questions, seeking clarification on the stories allocated to the sprint. They will often also demonstrate progress to the Product Owner to get their feedback.

Reporting is not usually done in a formal way as Scrum is set up to be highly transparent. The main forms of reporting are the task board, which acts as an information radiator, and the daily stand-ups that non-team members can attend (but not interrupt) and get a feel for what is going on.

Remember that agile encourages communication and interaction over process. As there is much interaction between the team and the Product Owner there is rarely any need for other reporting tools.

There is no obligation on the team to complete the work allocated to the sprint. Instead, they work their way through the items as best they can and striving to achieve an agreed definition of 'done' for each item. If there are stories incomplete at the end of the sprint they do not count towards the measurement of the team's velocity. That way the actual rate of progress is used to drive the team's capacity planning. The intention being to achieve a sustainable pace that maintains quality.

2

Sprint Planning is a formal ceremony where the team commits to the work that they would be able to accomplish during the sprint. It is where the stories prioritized by the PO are analyzed and broken into smaller technical tasks by the team.

Can you use PMBOK artifacts to guide the sprint? Technically speaking, yes you can because scrum doesn't prescribe how a team handles its sprint. But, since scrum is meant to be transparent, the information is supposed to come automatically from the sprint board, sprint burndown chart and the daily standups. so, you shouldn't need to improvise to get more data. Moreover, scrum is meant to convert the teams into self-organizing. So, guiding them from outside is usually not required.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.