I have MS Project server 2013 integrated with SharePoint 2013. I have created PWA site and in task page I want to add milestone as we do in MS Project professional 2013 but I don't see any options, any help will be appreciated
-
What is PWA site? – Mark C. Wallace Mar 30 '15 at 11:01
-
Project web app site – Mehdi Jalal Mar 31 '15 at 4:24
Just set the task to 0 duration. If your permissions allow this operation, that will change it to a milestone.
This is a classic permission issue. You probably have been granted as "Team member only, therefore your actions are limited to:
- Add a task to your task status
- Assigning a task to another resource
- Print a view
- Create, view, and link project issues and risks
- Approve or reject task updates
- Get e-mail alerts or reminders when tasks change
If you are the one creating / removing tasks and milestones, you should be granted a Project Manager role