6

I have MS Project server 2013 integrated with SharePoint 2013. I have created PWA site and in task page I want to add milestone as we do in MS Project professional 2013 but I don't see any options, any help will be appreciated

1

Just set the task to 0 duration. If your permissions allow this operation, that will change it to a milestone.

0

This is a classic permission issue. You probably have been granted as "Team member only, therefore your actions are limited to:

  • Add a task to your task status
  • Assigning a task to another resource
  • Print a view
  • Create, view, and link project issues and risks
  • Approve or reject task updates
  • Get e-mail alerts or reminders when tasks change

If you are the one creating / removing tasks and milestones, you should be granted a Project Manager role

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.