I am setting up a project in 2010; I have tasks, subtasks, predecessors but no resources assigned.
I have a task dependency that should start April 3 based on the predecessor finishing April 2. There is a separate tasks' subtask that has the main task as a predecessor. The dependency is finish to start, which means when the predecessor task finishes, the new task can start. The predecessor task is scheduled to finish July 14; the dependent task keeps auto scheduling to July 13! I cannot figure out what the problem is, and it is driving me nuts!