I'm using MS Project 2010 with a custom view that is showing baseline start/finish as well as start/finish fields of the tasks. I have modified the Gantt chart on the right hand side by cutting all rows in the "bar styles" list and inserting just bars for baseline tasks, baseline summary tasks and baseline milestones - this is showed correctly in my view. The problem now is that when I want to print this view, it prints the start/finish dates of the tasks as well as dependency lines - not the baseline tasks.
How can I fix this? I want to print just the baseline bars without dependencies.