Microsoft Project 2013:
Are there any default fields which show Time & Date when a task was FIRST CREATED, and when it was LAST EDITED ?
I would like to filter for tasks which lately have been added or updated into the whole project.
Project Management Stack Exchange is a question and answer site for project managers. It only takes a minute to sign up.
Sign up to join this communityThere is a 'Created' field, but no updated field. You can compare two saved copies of a file using the Compare Projects command - Report tab. The Compare projects allows you to compare two copies (Save As) of the same file and will generate a third project file to show added tasks, deleted tasks, and changes in task or resource data.