I am scheduling a series of 30 small training sessions (2,5d each), and I wish that each training would not be Split by weekends or holidays. All tasks are to be performed by the same person.

If training is scheduled to begin on a Friday, for instance, and to continue on Monday and Tuesday, I'd like to have it postponed to Monday.

Is there a way to automatically doing it?

1 Answer 1

1

A couple of assumptions and feel free to adjust to your specific scenario.

If the sessions are 2.5 days each, they cannot start after 1:00 pm on Wed. Create a calendar with working time Monday through Wednesday at 1:00 pm. Make Wednesday after 1:00 pm all day Thursday, Friday, Saturday, and Sunday nonworking. Make sure the calendar also has the standard holidays that you've included in the regular project calendar.

Create a 1 minute predecessor to the training sessions and assign the custom calendar to that task. If the 1 minute predecessor falls outside the working time allowed for the sessions, it will be rescheduled to the next working day (Monday).

2
  • Thanks for the suggestion. But case i have a Holiday on Tuesday, it looks like splitting will happen anyway.
    – Morts
    May 18, 2015 at 17:11
  • If you have a Tuesday holiday and don't want the session to be split - you'll need to make that entire week non-working in the calendar for the "buffer" task. If you don't want the event split and it takes 2.5 days - then it has to start either Monday, Tuesday, or by 1:00 pm Wednesday. In the case of a Tuesday holiday, I'd make both Monday and Tuesday of those weeks non-working. The event needs to start on Wednesday in that circumstance.
    – JulieS
    May 18, 2015 at 21:00