Suppose I have a task that is being stopped for a while and then it continues.

I would like to show that like recurrent tasks , is this possible with manual tasks ?

0

Yes. You can split the tasks. However, depending on why it stops and starts, might be better to create a separate task on another line.

6
  • How to do that split ?? Please ?
    – user17770
    Jul 15 '15 at 6:51
  • 1
    @OSryx Select the task that you want to split and click on the "Split Task" button in the Task ribbon. A split will be introduced at the "completed-to" point and you can then move the rightmost section to a new date. This works for auto and manual scheduled tasks.
    – Marv Mills
    Jul 15 '15 at 10:15
  • can you edit the answer so that I validate it :)
    – user17770
    Jul 15 '15 at 10:38
  • and I need more details about the fields/columns updated with the new dates .... can you help please @MarvMills
    – user17770
    Jul 15 '15 at 11:59
  • @OSryx Add new questions on this site (i.e. not tagged on to this question, answer or comments) and I and the community may be able to help. We do not offer 1-on-1 consultation!
    – Marv Mills
    Jul 15 '15 at 12:01

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy