I would like to compute the real finish date, I mean :
If Start date is 01/01/2015. and the Duration is 7 days , the real finish date is supposed to be 07/01/2015 (or at least 08/01/2015).
Please how to do that under Microsoft Project 2013 ??
Do I use a formula in custom field ? for instance :
DateAdd("m";[NumberOfDuration];[Start])