0

I am using Microsoft Project 2013.

I would like to visualize in the Timeline the percentage of completed task, for example 33%...

timeline

Is this possible ?

0

You can't add the percentage of completed task to the timeline boxes. Other option would be to manually color the tasks based of some criteria (not started, started, finished).

Timeline a,b,c

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy