I am using Microsoft Project Standard 2013 and would like to know how I can add a split task to my gantt diagram.
This task shell visualize dates where no changes to our infrastructure are allowed. Therefor this task has more than one beginning and ending. E.g:
- Task 1: 1th of June to 31th of August
- Task 2: 1th of July to 31th of August
- Frozen Zone: 1th of August to 4th August and 29th of August to 31th of August
I hope you understand what I am trying to achieve.