I'm having trouble to schedule a task that has two date constraints:
- It must happen 5 days after a precedessor task;
- It must happen on Mondays.
I tried creating and using an specific calendar, that only has Mondays as work days, but it didn't work out when I inserted the 5 days of latency.
I'm using MS Project 2003.
Thanks a lot!