2

I'm having trouble to schedule a task that has two date constraints:

  1. It must happen 5 days after a precedessor task;
  2. It must happen on Mondays.

I tried creating and using an specific calendar, that only has Mondays as work days, but it didn't work out when I inserted the 5 days of latency.

I'm using MS Project 2003.

Thanks a lot!

2
  • What should happen if 5 days after the predecessor is actually a Tuesday? Does it slip to the following Monday or does the predecessor move back to allow it to start on Monday?
    – Marv Mills
    Aug 17 '15 at 12:44
  • Hi Marv, it should slip to the next Monday. Thank you!
    – Edmon
    Aug 17 '15 at 12:50
3

On the basis it should slip to the following Monday-

  1. Add a milestone that depends on the predecessor with a lag of five days and add that milestone as a predecessor to your Monday task.

  2. Then we have the issue of only starting on Monday in MS-Project 2003. I cannot recall, but I don't think 2003 had task calendars. If that is true you will need to create a resource calendar with only Monday as a working day, then create a small task (say 1 minute) and allocate to that task a resource that uses the only-Monday calendar. That forces your short task to start only on Monday. Then add that short task as a predecessor to your task, ensuring the resources assigned to that task work normal hours.

Point 1. will give you a minimum 5 day lag and point 2 will ensure the task has to start on a Monday.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.