With User Story Mapping, If we start our sprint with the MVP, by definition the stories will be musts. In a fixed time-scale without shoulds and coulds, then how can we hit our targets if estimated velocity were to slip?

Usually in scrum, a feature delivered in a sprint would be a mix of musts, shoulds and coulds, allowing leeway for the PM to de scope some stories to keep on time-line.

2 Answers 2

5

I would look on a Story Map as on probability distribution. If the team decreases velocity in one sprint, it still have the room to increase it in the next one and deliver MVP in total, meeting the deadline.

enter image description here

2
  • So we are talking about the initial tranche of stories being, perhaps 'Must for Release but only Should for timebox? That would make sense. The only danger there is the slippage is starting to build a head of steam. Commented Aug 19, 2015 at 7:01
  • True, and with the assumption that most important stories are on a top you should have your MVP faster. The thing about a looking on a story map as a probability distribution is that if the team need to aim for a deadline, you can determine it for all of the known stories, knowing that it's 50% of chance to do them all. At the same time, as a smart PO, you'll try to fit all MVP stories close to the top, giving them way higher chances to be completed. Commented Aug 19, 2015 at 9:31
4

So first thing is to "pretend" it's MoSCoW, so when you plan, work on 60% velocity (this is before you've given a commitment to the fixed end date), better to over deliver than just meet the requirement. Once you are going, if you can't descope, you need to do the effort/quality thing. Look at your team and plan early to get extra resource (you ideally need people from inside so little/no ramp up, or screen carefully when bringing in), plus you need to think early about extra hours and if they help (a few here and there is better than a death march in the last month).

Also you need to pare work down to the bone. Agile is about YAGNI etc, but I mean everything, preemptive design, refactoring, test coverage etc. The MVP is a MINIMUM, so do only what you need. raise stories if something will need to be revisited later, just make sure you agree with the PO to spend a percentage time once the MVP is out and making money to clean up.

And if that's unpalatable, you need to remember something has to slip, and you are sacrificing quality in a controlled way you can fix later, better than team cutting corners on the fly to meet the deadline.

1
  • Looks like a real world comment. Commented Aug 19, 2015 at 8:53

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.