I have a project with a slew of tasks. Let's say for the sake of example I have 5 tasks and these 5 tasks will take 5 calendar days to execute. But, due to the nature of the task, a resource can only work 2 hours a day on the task due to the nature of the task.

Is there a way to create a task in project such that is has a duration, but does not fully impact the resource over that duration?

1 Answer 1

1

No, I'm afraid not. Tasks by themselves know nothing about how much work a resource or resources will perform. However, you can assign resource such that they don't work "fulltime" on the task. A couple of options:

  • Create the 5 day duration task and temporarily set it as Fixed Duration.
  • Use the Task Form to assign the resource and enter 10 hours of work.

Project will calculate the Peak units necessary to spread the 10 hours of work evenly across the 5 day duration. I would then, personally, return the task to either Fixed Units, or Fixed work.

1
  • This is essentially the work-around I discovered. Set the duration, then i the resource view reduce the amount of hours the task will take.
    – ngramsky
    Aug 28, 2015 at 16:05

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.