In MS Project (current version), I have the following task setup and can't find a solution:
Short translation for columns:
Vorgangsname = Taskname
Arbeit = Work
Dauer = Duration
Anfang = Beginning
Ende = End
Not visible in the screenshot: Both tasks have the fixed day 2015-10-05 (Monday) and the resource-availability is 50% (global setting).
My question is: How can both tasks begin on the same day without a resource-conflict? My suggestion is, to change the percentage of the resource-availability per task, but I don't know where to find that setting.