Example: new housing scheme, constructing 10 houses on separate plots. Brickwork can begin 5 days after the 20-day tasks of scaffolding being erected. However, brickwork can't finish until 5 days after scaffolding has finished being erected.
How do I link the start & finish of the brickwork to the start and finish dates of the scaffolding being put up? MSProject says I can't give one task 2 links to the same predecessor task.....
All help gratefully received..